22 November 2018

Difference between Change Control and Configuration Management

Project Management Professional (PMP) students often confuse Integrated Change Control (ICC) and Configuration Management (CM). To put this very simply, ICC controls change whereas CM controls the records of all approved work.

Configuration Management


There are two types of changes. One moves forward whereas the other move backward or sideways. (The are not PMI terms. I use them just to help you picture the differences.)

Forward change is normal work as it happens according to plan. You submit the Project Management Plan and ongoing work to CM when they are done and approved by reviewers. The main purpose of CM is to make sure everybody bases new work on the latest, approved plans and work.

CM also provides and controls the repository for work history, process assets, and lessons learned. Once work has been approved and entered into CM, it becomes subject to change control.

Integrated Change Control 


Backward changes revise work already done. Sideways work requires changing the Project Management Plan or design plans before moving forward. All changes to the plan or to previous work go through ICC. The ICC procedure ensures that you consider the alternative measures and the effects that a change can have. Passing the change through the ICC Board ensures that people with various perspectives can identify stakeholders and impacts you did not think of. This procedure enables making informed decisions.

The change request and the ICC Board's decision are stored by CM. If the change is approved, the change has to be implemented, and the records of the change (for example, approved, revised documents) are stored by CM. CM usually has responsibility for notifying the stakeholders in accordance with the communications plan.

Think of the ICC as the process for making sure changes to existing plans and work are done the right way. Think of CM as the library where all approved plans and work, including changes, are stored.

20 August 2018

Project Manager and PMP Candidate Resources

I will add resources to this list as I come across them or as you identify them in your comments.  With my budget, the emphasis will be on free resources.

Webinars

Podcasts

  • Elise Stevens @ElisethePm
  • Lean Blog
  • People & Projects
  • Gemba Academy
  • Mastering Business Analysis
  • PM for the Masses
  • http://Manager-Tools.com

Sample Questions and Mock Exams

- Beware outdated content. Don't waste your time with any mock exam whose site does not clearly identify it as based on PMBOK 6.

PM Social Media Communities

- The lists below are in no particular order, and my listing of any group does not necessarily constitute a recommendation.
- Study tip: When studying sample questions posted online, look up the answers in the PMBOK and explain why the best answers are best and the other answers are less than best. Having to form complete thoughts helps you internalize the material and helps others learn, too.

LinkedIn
Google Plus
Facebook
- Requests for stolen IP are rampant in some of the Facebook groups. Please join me in discouraging it.
- Some sellers of test materials post the same sample questions in many PMP study groups, and their questions dominate the less-active groups; so many of the groups add little unique value.

Future Additions to This Page or New Pages

  • Business Analysis Resources
  • Continuous Improvement Resources

28 February 2015

The Black Hole of the Agile World: Systems Thinking

Agile fanatics (excuse me: practitioners) love to do things in tiny increments.

That's OK for products where bite-sized deliveries have value, but it's fantasyland for many real-world projects.

Take, for example, the design of a new car. Sure, you can break the car into systems -- chassis, body, safety package, motor, and so on. Waterfall does that, too, but let's consider the airflow over the body. The airflow is affected by the whole assembly. Every part affects the whole. You can't just design a fender in isolation and say, "Looky, looky, I've delivered value!" No, you've delivered an irrelevant piece of scrap.

In any course on Business Analysis, the importance of a unit on Systems Thinking cannot be overemphasized because the Agile world has completely forgotten its value. 

Before the 1990's, there was a role called Systems Engineer.

That title is still around, but the job is not. At least, the job has become a rare grain of wheat a vast field of tares.

A Systems Engineer had many skills of a project manager, a BA, a Systems Thinker, and a cross-disciplinary engineer, all rolled into one.



Along come companies such as Microsoft and Cisco, dropping the qualifying word from titles such as Network Systems Engineer, Software Systems Engineer, and Server Systems Engineer. Suddenly, every engineer, analyst, and administrator is a Systems Engineer. I wish I had a paycheck for every time a recruiter has contacted me with a so-called Systems Engineer job that turned out to be for an IT admin or a software coder.

True Systems Engineering jobs have become needles in a field of haystacks, and systems thinking has almost been forgotten.

Thousands of Systems Engineers lost their jobs due to decimation of the US Defense sector in 2009. (I proud of myself for not pointing out the predictable political element of that.) They still find three strikes against them:
  1. Transitioning to a different job category such as Project Management or Business Analysis
  2. Getting a foot in the door of a different industry (other than fast food)
  3. Living in a job market where all the growth is in part-time service jobs and has gone to low-skilled workers
Hiring managers would do well to consider bringing in experienced cross-disciplinary, systems thinkers. It would not take much training to bring them up to speed in new roles such as PM or BA.

Have you ever thought of a project as a system of people, or a product as a system of technologies? Systems Engineers do that instinctively, and such integrated systems thinking could prevent a lot of headaches for maturing companies.

Now, if you'll pardon me; I need to clean up a spill in aisle five.

01 June 2014

Differences between Risks and Issues, Part 2

Differences between Risks and Issues, Part 2

Threats; and Another Side of Risk

 
Part 1 (click here) of this series defined issue.

Threat versus Risk

If a situation, such as a cause and its effect, is certain, then it is an issue. With risk, we deal with uncertainty. If the probability of something is zero, it has no uncertainty. If the probability is 100%, again, it has no uncertainty. The term Risk only applies when

0% < probability < 100%

In Risk Management, we avoid the term "threat" because in everyday discussion, "threat" could also mean "promise of harm" or "logical sequence resulting in harm."

For example, a bully "threatens" to call you a bad name. If we believe the bully, this type of threat would be an issue, not a risk, because there is no uncertainty. If we don't care what the bully says, there is no effect, so it is neither a risk nor an issue.

Another side of risk

Most explanations of risk concentrate on the probability of the event. What if the event is certain, but you don't know what the effects will be?

Risk has two real parts:
  • Cause - A condition or possible change in conditions
  • Result - The effect that may happen
Risk has a probabilistic part, too:
  • Uncertainty
PMP study materials usually focus on uncertainty about whether the cause will happen. However, we can also have uncertainty about what effect a condition or change in conditions may cause.

Therefore, a condition (or change) may be certain, but you still have risk if you have uncertainty about the results.

As PMs, we are communicators. We listen. Others often use terms and definitions different from ours. So we ask people what they mean and negotiate a common vocabulary. We do this to control the risk of broken communications.

If we find that somebody says "the bully is a threat" and means "the bully poses a risk," then we could enter this in the Risk Log in one of three ways:
  • There is x% chance that the bully will call another worker a bad name, causing that worker to quit.
  • The bully will call another worker a bad name, and there is y% chance that the other worker will quit.
  • There is x% chance that the bully will call another worker a bad name and y% chance that the other worker will quit.
If there is 100% probability that the bully has or will call the coworker a bad name and a 100% probability that the coworker will or has quit, then we have an issue.

And if you go around calling my coworkers bad names, we have an issue.

Further study: Use a search engine to learn more about "aleatory variability" and "epistemic uncertainty." However, please don't ask me about them because, the way other authors explain them, I do not understand at all.

(c) Copyright 2014, Richard Wheeler

24 June 2013

So You Failed PMI's CAPM Test?

This is your first practical lesson in Project Risk Management. When your customer (PMI) specifies a parameter (x%), determine a safety margin so that, if you take the test on a bad day, you will still pass.

How many times did you read Rita's book? Most people read it AND the PMBOK Guide at least twice.

How many practice test questions did you take? Many people take thousands. (You can easily find thousands of free PMP practice questions on the web, although many are outdated and few will be up-to-date after July 31. CAPM questions are much harder to find.)

When you took the practice tests, did you research the answers you got wrong? Did you research the answers you had to guess at? Memorizing will only get you part way through PMI's tests; you need to dig and understand the material.

If you are taking the CAPM, you must want to become a PMP. Consider studying for the PMP exam. The deeper knowledge will give you understanding that goes beyond mere memorization for the CAPM exam. Also, for the PMP exam, you need to have 35 contact hours. Again, the extra effort would help you with the CAPM exam.

The two books I've heard the best reports about are Rita's books and the Head First books. You can also find many free podcasts on the web and on iTunes.

Two names to look for are Oliver Lehmann and Cornelius Fitchner. Oliver has some free apps and the best sample question on the web. Cornelius has some great 'casts, some of which are free.

Finally, when you have a tough time with some concept or a sample exam question, feel free to ask about it in the Google+ group, "Project Management, PMI, PMP Certification." Ask under the tab "PMP preparation questions." (Out of respect for copyrights, please identify the source of quotes.)

Other than that, I suppose there's not much you can do.

See Also


Copyright 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.
 
IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees when you attend the live session. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

05 June 2013

Study Plan for PMP Certification (Early June 2013)

It's a little late to start studying for the PMBOK Guide, 4th edition, test. First, you have less than two months to join PMI, apply for the exam, prep for it, and arrange a test date, and pass the exam.   Second, the 5th edition is out, so a significant portion of knowledge based on the 4th edition is already obsolete.  Third, lots of people need to retake the exam; so if you need to retake the exam, you will have to re-study for the 5th edition test.
 
Classroom interaction is great, but online training has a lot of advantages, too. With my budget, schedule, and remote location, distance learning is an absolute must.  If I had the budget, I would take the training offered by Cornelius Fitchner at PM-Prepcast. Cornelius is also on Facebook at Project Management Prepcast.
 
I would add some warnings.  Preparing for the PMP exam should not be about learning to take the exam.  Boot camps teach to the exam.   That's alright, as long as you understand that a boot camp is just an orientation.  The learning takes place when you

 - Read the PMBOK Guide at least twice.
 - Master the material in one of the great reference books out there. (1)
 - Research the answers to a thousand or so practice questions. (2)

Finally, join the Project Management, PMI, PMP Certification community on Google+.  When you get stumped by a topic or a sample question, share your question.  We LIKE helping each other because, if something stumps one person, others probably have difficulty with it, too.  Besides, it drives us to learn the material. (3)

Studying for the PMP exam is just a starting point.  Getting a piece of wallpaper may help you get a job, but if you want a career, use your certification as a springboard to deeper studies of PM topics and further certifications.

Footnotes

(1) Rita Mulcahey's PMP Exam Prep has a wealth of information, and the Head First PMP book has gotten a lot of recommendations, too.
 
(2) Cornelius Fitchner has listed a number of free exam question sources on one of his sites. Make sure the questions correspond to the edition of the PMBOK Guide for which you plan to take the test.
 
(3) "Fair Use" allows sharing a limited number of questions for critique or discussion. To be fair to the person who wrote the question, cite the source; and to help the rest of us, provide a link.
 
Copyright 2011, 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

24 March 2013

Project Management and Open Communications

Project Managers need to guard against setting up an environment where bad news never reaches them. They need to praise and encourage those who communicate risks before they become issues, issues before they become problems, and problems before they become project failures.

Some managers remind me of the Clinton trial in the Senate, following his impeachment in the House.

The Senate set up a rule requiring Ken Starr to keep all the records and evidence in another building. Bringing it to their offices without an invitation would have violated protocol.

Then the majority of senators refused to go view the evidence. A few who did view it said they came away weeping, and the rest (having refused to view the evidence) said that they lacked evidence sufficient to convict.

Does your comfort zone tempt you to maintain willful ignorance? Does your character allow reliance on plausible deniability? The PM has accountability for project success, which any lack of awareness may bring about; but that accountability extends to achieving success ethically.
 
I wonder:  Do PMs ever include ethical lapses as project risks?

23 March 2013

The Best Project Management Software

Project management covers many knowledge areas. Developers approach PM software functionality from the perspective of a particular discipline or PM knowledge area. The approaches usually focus on a narrow selection of the following needs:
  • Requirements
  • Software Development Life Cycle (SDLC)
  • Agile methods
  • Model Based Systems Engineering (MBSE)
  • General verification/validation
  • Software test management
  • Software test management with scripting
  • Issue and change management
  • Product definition from a market research angle
  • Scheduling
  • Cost management
  • Resource management
  • Project communications
  • Scope and requirements definition
  • Quality management
  • Configuration management
As a result, all the solutions I have looked at work for only a small portion of project management. For example, MS Project would be useless for requirements management, and DOORS would be useless for project scheduling.
 
Some developers stress integration of their products with other products -- preferably their own. For example, Rational (specializing in SDLC) bought DOORS and worked on integrating the two product lines. Then IBM bought Rational and expanded the integration effort to include other IBM products.
 
Implementing many PM software products and then tailoring them to the organization's needs can require permanent, trained resources. Integrating several products can take years, even in large organizations.
 
With the current state, I believe any attempt at a total PM solution will require a very large initial effort, significant support to maintain the solution, and an acceptance that some interfaces between PM processes just have to be done by hand.
 
Therefore, to answer the question, "What is the best software/tool for end-to-end Project Management?" you need to prioritize the areas of PM because no product addresses the end-to-end needs -- or at least, the top-to-bottom needs.

Life Cycle Costing for Projects

Defining Life Cycle Costing

Life cycle costing (LCC) looks at the cost of the whole life of the product, not just the cost of the project. A product has two major cost phases, the project phase that designs and produces the product, and the O&M phase where the owner operates, maintains, and decommissions the product.

(A lot of Project Managers (PMs) forget decommissioning. As an extreme example, consider how much it will cost to maintain and protect a nuclear waste site for the next 500,000 years.)

The design philosophy is part of the project scope.  The customer may want a cheap, disposable product, so the design team would not put much effort into designing for low maintenance, low manning, and long lifespan.

On the other hand, the customer may need the product to last a long time.  Operations costs can include:
  • building more units
  • maintaining equipment
  • training users
  • expanding, upgrading, or re-purposing the product
  • providing consumables
  • procuring replacement and spare parts
  • transporting, installing, or disposing of waste
Operations can far outweigh the initial cost.

The scope statement, the Statement of Work, the nature of the product, industry standards or government regulations, and the user needs can guide decisions about what aspects, if any, of life cycle costing to include in project planning.

What LCC Means to the Project

Considering operations and maintenance costs requires including, as part of the scope, performing the project in such a way as to keep O&M costs down for the customer.

For example, easy access to a car's timing belt decreases the amount of labor the owner has to pay to have it replaced, and using a steel widget instead of an iron one results in fewer failures due to corrosion.  Such steps will increase the cost of the project, but they may decrease the customer's total cost of ownership.

Considering operations and maintenance costs also requires estimating the cost of the entire product life cycle.

A point exists where spending more on reducing O&M costs would not cut total cost of ownership.  For example, making windshields out of the material they use in Soyuz windows might mean never having to replace cracked glass after a bird hit, but it would cost more than the rest of the car.

For this reason, the project will include a trade study that estimates the total of both the project cost and all the costs incurred by the customer after product delivery.  As its goal, the study will recommend ways to minimize the total cost.

What LCC Means to the Project Manager

The PM should consider the following steps to ensure project success:
  • Make sure the customer considers cost of ownership and agrees to LCC goals.
  • Ensure that project scope and project requirements clarify LCC goals.
  • During project planning, account for the effects of those requirements on the project.
  • Oversee a trade study to determine the best compromise between project cost and O&M costs before project planning is finalized.
  • Make sure the customer understands cost tradeoffs between a cheap project and a project that produces a product with characteristics such as longer life, less expensive maintenance, and greater safety.
  • Get approval of the LCC strategy from the customer and authorization to follow that strategy from the project's sponsor or management.
Please let me know in the comments if you have any corrections or additions.

19 March 2013

Life Cycle Costing for Project Planning

Life cycle costing looks at the cost of the whole life of the product, not just the cost of the project.

A product has two major groups of life cycle phases, the project phases that conceive, design, produce, and deliver the product, and the Operations and Maintenance (O&M) phases where the owner operates, maintains, and decommissions the product.

Some products also have phases where proof of concept testing, design refinement, and prototyping overlap with O&M phases.

(A lot of PMs forget decommissioning. As an extreme example, think about how a chemical or nuclear waste site might require maintenance and protection for the nest 500,000 years.)

The project scope should define the design philosophy. The customer may want a cheap, disposable product, so the design team would not put much effort into designing for low maintenance, low manning, or long service life.

On the other hand, Operations costs such as building more units, maintenance, training users, expansion and modification, providing consumables, transporting, installing, and disposing of waste can far outweigh the initial costs.

The scope statement and the nature of the product will guide in deciding which aspects, if any, of life cycle costing to include in project planning.

12 March 2013

Difference between Quality Assurance and Quality Control

Major Differences between QA and QC

The difference between Quality Assurance (QA) and Quality Control (QC) can easily get lost among all the words. Some simple contrasts will help separate the two in your mind.
 
1. QA is primarily proactive. QC is primarily reactive.
 
2. QA focuses on the methods. QC focuses on the results.
 
3. QA uses some statistical methods to analyze how work is done, but QC uses a lot of measurements and statistics to make sure you get the right results.
 
4. QA's scope how the project gets done, whereas QC's scope includes how well the work got done and how well the product or service meet the requirements.
 
Putting those together, Quality Assurance assures you will get the product or service right by making sure the work gets done using the best methods. Quality Control measures and analyzes to control the quality of the product, service, or project execution, and to verify whether it meets the requirements.
 
If you view your studies of QA and QC with this framework in mind, the rest of the differences will make a lot more sense.
 
Example
 
I like food, so let's use a restaurant as an example.  Normally a restaurant would be Operations (not Project), so let's assume that our fine establishment will cater an event and, therefore, Chef Boyardee has a project to manage.

QA (proActive Execution) may find weaknesses in processes or standards due to problems that have occurred. For example, Waiter A wanted to take a break, but Waiter B did not know to whom to deliver the food. We have identified a new stakeholder requirement: Waiters need the ability to hand off orders to each other.

The head waiter improves the process by requiring all waiters to include the table number and seat code for each order. Thus, QA reacts to the problem, focuses on the processes and tools, and enables improvements to the project.

QC (reactive Control) may find a trend indicating an approaching problem. The Chef inspects the food before it is served and notices less steam rising from the tandoori vegetables. Although the food is still acceptable, the temperatures are trending downward.

Before customers start receiving food below the Lower Control Limit of temperature, the Chef determines that the tandoori cook's burners are not getting enough propane. The Chef alerts the cook, who swaps in a fresh propane tank.

Thus, QC Monitored the product, analyzed the data, performed a Root Cause Analysis, and enabled proactive control of an issue before it became a problem.
 
Warnings about Generalizations
 
Remember, "proactive" and "reactive" are generalization to differentiate the two processes. QA (proActive Execution) can be reactive and QC (reactive Control) can be proactive, as well.
Is it safe to say that QA involves polices and procedures ... while QC involves actual work on a product or service?
Yes, as a generalization, it is "safe to say that QA involves polices and procedures ... while QC involves actual work on product or service."
 
One important note: Process and procedure are ambiguous terms, and every organization has its own definitions of them. Both QA and QC can initiate improvements to (processes or procedures).
 
For example, one level of (process or procedure) might instruct personnel to collect the materials and drawings, then have the machinist construct the widget, then have QC inspect it.
 
Another level of (process or procedure) might instruct the machinist how to program the machine, mount the raw materials, push the buttons, release and label the widget, dispose the scrap, and prepare the machine for the next task.
 
From that point of view, QA might perform quality audits to verify that a high level (process or procedure) is being followed, but QC might verify that a detail-level (process or procedure) was followed correctly and with the right results. Both QA and QC involve (processes or procedures).
 
Reminder:  This discussion is just about the major differences. When you look at the details and the ambiguous terms makes it confusing, refer back to the big picture for perspective.

11 March 2013

Slack, Float, and Critical Path Methodology

So as the PM I want to locate the longest path, because it will assure that I meet the project deadline.
Correct. But don't look for the "longest path," look for the "critical path." They are the same, but when you say critical path, you indicate that you know the best way to find it.
The shortest path, which has no slack, tells you as the PM that you will not be able to meet the deadline for the project.
Forget 'shortest path.' What tells you that you will not be able to meet the deadline is an end-to-end path having "negative slack." More about that later.
 
Slack is about an individual activity. Float is about how that activity's slack relates to the activities around it. They are the same thing viewed from slightly different perspectives.
 
Here's a source of confusion that I have yet to seen or hear anyone explain: For the critical path, we look for a path from the Start to Finish that has either zero or a negative number for the slack of all its activities. When we talk about a path that has slack (for example, 2 days), however, we talk about that single branch, not about a whole Start-to-Finish path.
 
Did you do connect-the-dots pictures as a child? Lets do a mental experiment. Imagine replacing all the boxes in a network diagram with their slack numbers. If there is enough time to do the project, you will see a path of zeroes from Start to Finish. In your mind, go over that path with a highlighter. That is the critical path. The durations of those boxes add up to the shortest time in which the project can be completed.
 
Suppose you add up the durations of the activities along the critical path, and the sum is 42 days. If the deadline is in seven weeks (49 days), then you have enough time.
 
If Sales promised the customer the project would be done in 40 days, but the project requires 42 days, then instead of having zeroes along the critical path, you will have negative twos (-2s). This is called negative slack. You will need to use schedule compression techniques to reduce the length of the project.
 
Note that the last two paragraphs involved only the critical path activities. None of the paths that you did not highlight in the first paragraph matter. They are all irrelevant -- up to this point.
 
Slack is also called "float" because you can move the activity forward up three days. Imagine a small cereal bowl floating in a large sink. It has room to float around. The bounds within which it can float are set by the edges of the sink. Similarly, an activity with positive slack can float within bounds set by parallel activities in the critical path.
 
Here's another confusing point. Suppose activities B and C are parallel to each other. That is, both can start as soon as activity A is done, but both must by done before activity D can start.
 
Activity B
Slack = 2 days
Duration = 4 days
 
Activity C
Slack = 0 days
Duration = 6 days
 
How long will the path that contains Activity B take? If you answered, 4 days, think again. Suppose activity A ends on day 10. Activity C takes 6 days, so activity D cannot start until day 16. So how long does the path containing activity B take? The path takes 4 days of activity plus two days of slack. It takes the same time as the longer activity (C) that it parallels.
 
Two activities done in parallel cannot be completed any faster than the longer activity. For this reason, it is a waste of time to look for "shorter" Start-to-Finish paths.
 
Activities or paths with slack (float) do not affect how long the project takes. However, there are two exceptions.
 
First, if the PM uses schedule compression techniques to shorten the project (for example, from 42 days to 40 days), then at least some of the activity durations or the relationships between activities change.
 
When the PM recalculates how long the project will take, the critical path may change. One critical path activity that had -2 slack might now have a slack of 1, so it is no longer on the critical path; and another activity that formerly had a slack of +1 and was not on the critical path may now have a slack of zero and lie on the critical path.
 
Second, every activity has risk. You can lower the risk of a non critical path activity by starting it early. You cannot do that with a critical path activity, so it carries more risk. If something goes wrong with a non critical path activity, if it takes long enough, it can still prevent the start of a critical path activity that follows it. On paper during planning, it does not affect the project's duration, but during execution, it can.
 
I hope I clarified more than I confused. Good luck!

24 February 2013

Project Selection

For project selection, the Project Management Institute's (PMI's) Project Management Body of Knowledge (PMBOK) Guide assumes you have more than one project from which to choose. By analyzing the options, you can determine which has the greatest value to the company. The formal method for choosing the best option is called a project selection method.
 
Suppose I have to choose between
  • fixing my child's favorite meal and leftovers for my wife, or
  • fixing my spouse's favorite and cheese mac for my child.
So I ask, "which gives me the better Return on Investment (ROI)?" To answer the question, I consider
  • How much time and money it will take
  • How much of a mess I will have to clean up
  • Does it align with my goals (fun vs. study time)
  • Rewards (somebody else WILLINGLY taking out the trash)
  • How long it will take to reap the rewards
  • Risks (what if I overcook the macaroni? or burn the steak?)
A Project Manager (PM) will place a priority on each criterion and score the probable outcomes. The sum of the weighted scores for each option yields a total score for that option.
I did this with my daughter last year when she needed to buy a car. The result surprised me and was not at all what I expected, but it turned out to be a great choice.

The primary use of project selection is for choosing between projects. However, one can also used it during the project life cycle. The projected ROI of a project can change, for example, due to changing market or regulatory conditions. If the ROI falls, it might be worth canceling the project so the funds and resources can be applied to a more promising project. This is a special case of selecting between competing opportunities.
 
The executives of a company I won't name signed a contract to deliver a product on a certain date. If the company failed to deliver on that date, the company would have to pay liquidated damages; and if the company canceled the project, it would have to pay penalties.
 
Unfortunately, the executives failed to have Engineering review the contract. It turned out that the company could not meet the deadline. The PM tried schedule compression, but as risks turned into issues, it became clear that the project could not meet its deadline.
 
What should they have done? The company should have used the project selection method to choose between
  • Completing the project and paying the liquidated damages
  • Canceling the project and paying the penalties.
Remember, the considerations aren't always directly related to the project. Things such as the company's reputation, the future value of establishing a market presence, or future business based on this project's design work have value, too. For example, cell phone companies often sell cell phones at a loss because they make their money on the service contracts.

Copyright 2011, Richard Wheeler

09 February 2013

Project Management Career Path

In terms of study, what path should one take to become a project manager?

First, unless you have several years of project management work experience, I would suggest obtaining the Project Management Institute's (PMI's) Certified Associate Project Manager (CAPM) certification. After that, study the qualifications for the Project Management Professional (PMP) certification and create a plan based on those qualifications. The plan should include studying PMI's Project Management Body of Knowledge (PMBOK) Guide and added studies based on the PMBOK Guide's process knowledge areas.

Second, familiarize yourself with the International Counsel on Systems Engineering (INCOSE) Systems Engineering Body of Knowledge (SEBOK). After achieving PMP certification, pursue INCOSE's certifications. PMI certification will give you a top-down perspective across all departments whereas INCOSE's certifications will give you a bottom-up understanding of the engineering processes and products.

Studying these two knowledge areas in this order should provide a faster path, on paper, to project management and beyond. However, if you would prefer a career path leading to a Chief Engineer title, you might reverse the order. Pursing Engineering in Training (EIT) and then Professional Engineer (PE) certifications would be valuable on the technical career path, too.

Third, study people, develop lots of relationships (focus on the personal aspects and what you can do for them, not on what you can get out of them), and find at least one mentor other than your supervisor. These are critical.