20 October 2016

Steps to Avoid Becoming Another Samsung

"What should I focus on or watch out for in order to prevent a calamity from happening to my business?"

Asked at http://www.mosaichub.com/answers/question/what-should-i-focus-on-or-watch-out-for-in-order-t#57652

Study Risk Management

  • I strongly suggest studying the Risk Management sections of Project Management Institute's (PMI's) Project Management Body of Knowledge Guide Guide (PMBOK). Add to that the corresponding chapter of a PMI-PMP (Project Management Professional) exam study guide such as the one by Rita Mulcahey.
  • If your organization can bear the cost, consider hiring an employee or consultant with a strong background in risk management to help establish a risk management program or to review the program you establish.
  • One such expert is Glen Alleman. I recommend the materials on his blog, Herding Cats.

Systematically Define Your Business and Identify Potential Risks

  • In general, you need to systematically define and examine every facet of your business, processes, products, services, and business environment. (The whole of the PMBOK Guide will help you classify those areas for projects.) As you examine each facet, you compile a list of risks. Clarification: I'm not saying you have to do it all at once.

Evaluate Risks

  • To evaluate the identified risks, you make a subjective, rough estimate of their effect and probability.

    Risk = Impact x Probability

    You then accept the low-risk items or place them on a watch list and make a more objective evaluation of high and medium risks.

Aleatory and Epistemic Risk

  • One of the characteristics of risk that you need to consider is what you know about the risk. Epistemic risks can be reduced by learning more about them. Aleatory risks cannot be reduced because there's a random element. For example, knowing how many sides dice have lets you know the possible range of values, and testing them can tell you whether loading or poor workmanship make some results more likely. On the other hand, after that, you cannot reduce randomness. This is part of the information you use when evaluating strategies for managing the risks.

Identify Candidate Responses

  • Identify possible responses (accept the risk, sidestep the risk (e.g., plan your road around the mountain instead of tunneling through it), reduce the effects, take steps to reduce the probability, transfer the risk to somebody else (outsourcing or insurance), or wait and see.

Evaluate, Select, and Implement Responses

  • Evaluate and select responses based on their cost and probability of success. Note that risk responses become policies, changes to processes, or new requirements. 

Monitor Responses and Watch List

  • Set up a risk monitoring system that tracks risks in the watch list as well as implementation of responses. This feeds into controlling performance and also into Lessons Learned (you have a Lessons Learned archive, don't you?) that save you work in the future.

Iterate and Integrate

  • Risk identification is iterative because risk responses can create secondary risks, because everything eventually changes, and because . Many companies miss new risks because they perform risk identification and planning and never re-visit the subject.
  • Many organizations delegate responses and leave them isolated from the . However, except for responses that are experimental (e.g., try it on a limited scale before rolling it out to the entire organization), they must be integrated into the business, project, product, etc.
  • Like process improvement, risk management (RM) needs to be part of a company's culture. Some say that RM should dominate status meetings because it is more proactive and more actionable, and also because "status" is actually a facet of risk.
Copyright 2016, Richard Wheeler

Steps to Avoid Becoming Another Samsung

"What should I focus on or watch out for in order to prevent a calamity from happening to my business?"

Asked at http://www.mosaichub.com/answers/question/what-should-i-focus-on-or-watch-out-for-in-order-t#57652

Study Risk Management

  • I strongly suggest studying the Risk Management sections of Project Management Institute's (PMI's) Project Management Body of Knowledge Guide Guide (PMBOK). Add to that the corresponding chapter of a PMI-PMP (Project Management Professional) exam study guide such as the one by Rita Mulcahey.
  • If your organization can bear the cost, consider hiring an employee or consultant with a strong background in risk management to help establish a risk management program or to review the program you establish.
  • One such expert is Glen Alleman. I recommend the materials on his blog, Herding Cats.

Systematically Define Your Business and Identify Potential Risks

  • In general, you need to systematically define and examine every facet of your business, processes, products, services, and business environment. (The whole of the PMBOK Guide will help you classify those areas for projects.) As you examine each facet, you compile a list of risks. Clarification: I'm not saying you have to do it all at once.

Evaluate Risks

  • To evaluate the identified risks, you make a subjective, rough estimate of their effect and probability.

    Risk = Impact x Probability

    You then accept the low-risk items or place them on a watch list and make a more objective evaluation of high and medium risks.

Aleatory and Epistemic Risk

  • One of the characteristics of risk that you need to consider is what you know about the risk. Epistemic risks can be reduced by learning more about them. Aleatory risks cannot be reduced because there's a random element. For example, knowing how many sides dice have lets you know the possible range of values, and testing them can tell you whether loading or poor workmanship make some results more likely. On the other hand, after that, you cannot reduce randomness. This is part of the information you use when evaluating strategies for managing the risks.

Identify Candidate Responses

  • Identify possible responses (accept the risk, sidestep the risk (e.g., plan your road around the mountain instead of tunneling through it), reduce the effects, take steps to reduce the probability, transfer the risk to somebody else (outsourcing or insurance), or wait and see.

Evaluate, Select, and Implement Responses

  • Evaluate and select responses based on their cost and probability of success. Note that risk responses become policies, changes to processes, or new requirements. 

Monitor Responses and Watch List

  • Set up a risk monitoring system that tracks risks in the watch list as well as implementation of responses. This feeds into controlling performance and also into Lessons Learned (you have a Lessons Learned archive, don't you?) that save you work in the future.

Iterate and Integrate

  • Risk identification is iterative because risk responses can create secondary risks, because everything eventually changes, and because . Many companies miss new risks because they perform risk identification and planning and never re-visit the subject.
  • Many organizations delegate responses and leave them isolated from the . However, except for responses that are experimental (e.g., try it on a limited scale before rolling it out to the entire organization), they must be integrated into the business, project, product, etc.
  • Like process improvement, risk management (RM) needs to be part of a company's culture. Some say that RM should dominate status meetings because it is more proactive and more actionable, and also because "status" is actually a facet of risk.
Copyright 2016, Richard Wheeler

22 July 2015

3 Factors in Risk Management: Probability, Impact, and Velocity

Risk Score

Qualitative and Quantitative Analyses in Project Risk Management both take into account Probability (P) and Impact (I). A Risk Score is the product of the two.
Qualitative Analyses use subjective estimates of probability and impact as a screening process that categorizes risks for management, monitoring, or ignoring. Risks placed in the management category go on to Quantitative Analysis and Risk Response Planning.

What about Urgency?

A third value should be considered: Velocity (V), which is the inverse of the time-to-impact.
Seldom can we deal with all risks at once. The value of considering Velocity lies in prioritizing further effort so you have enough time to respond to urgent risks. We would not consider Velocity when assigning risks to the three categories because we want to deal with the important things, not the urgent things. (Consider Pareto's 80/20 rule.)
If Probability times Impact describes an area, then to be consistent, we would add Velocity as a third dimension. That is,
Priority Score = Priority x Impact x Velocity

Another View of the Priority Score

Priority times Impact has another label, which is Expected Monetary Value (EMV). EMV is often used by itself for guiding decisions. If we express the Priority Score as
Priority Score = EMV x Velocity
then we give EMV a weight equal to the weight of Velocity.
The reason we would not consider the Velocity by itself goes back to the principle about the cost of rework. The later you deal with a problem, the more it costs because you have to repeat and fix work that came before. The previous effort becomes wasted, costs rise, schedule lags, and you have to use extra resources to get back on schedule.
Similarly, the longer you wait to deal with a risk, the more rework you have to do. Therefore, we need to factor both Velocity and EMV into prioritizing work: Velocity to deal with urgent risks, and EMV to control costs.

A New Step: Priority Analysis (when needed)

I recommend inserting a new step into Risk Management when there are risks with high velocity and you have to prioritize which risks to deal with first:
  1. Qualitative Analysis with Risk Score = estimated Priority x estimated Impact
  2. Priority Analysis with Priority Score = EMV x Velocity = Priority x Impact x Velocity
  3. Quantitative Analysis with Risk Score plus other factors such as Velocity and Cost Effectiveness
I bring up Cost Effectiveness because you want to ensure that you don't spend $150 to prevent a risk whose EMV is only $100.

Reference

Hall, Harry, PMP, PMI-RMP. 30 Quick Risk Evaluation Tips. PM South. http://www.pmsouth.com/2015/07/18/30-tips/. Accessed 21 July 2015.

01 June 2014

Differences between Risks and Issues, Part 2

Differences between Risks and Issues, Part 2

Threats; and Another Side of Risk

 
Part 1 (click here) of this series defined issue.

Threat versus Risk

If a situation, such as a cause and its effect, is certain, then it is an issue. With risk, we deal with uncertainty. If the probability of something is zero, it has no uncertainty. If the probability is 100%, again, it has no uncertainty. The term Risk only applies when

0% < probability < 100%

In Risk Management, we avoid the term "threat" because in everyday discussion, "threat" could also mean "promise of harm" or "logical sequence resulting in harm."

For example, a bully "threatens" to call you a bad name. If we believe the bully, this type of threat would be an issue, not a risk, because there is no uncertainty. If we don't care what the bully says, there is no effect, so it is neither a risk nor an issue.

Another side of risk

Most explanations of risk concentrate on the probability of the event. What if the event is certain, but you don't know what the effects will be?

Risk has two real parts:
  • Cause - A condition or possible change in conditions
  • Result - The effect that may happen
Risk has a probabilistic part, too:
  • Uncertainty
PMP study materials usually focus on uncertainty about whether the cause will happen. However, we can also have uncertainty about what effect a condition or change in conditions may cause.

Therefore, a condition (or change) may be certain, but you still have risk if you have uncertainty about the results.

As PMs, we are communicators. We listen. Others often use terms and definitions different from ours. So we ask people what they mean and negotiate a common vocabulary. We do this to control the risk of broken communications.

If we find that somebody says "the bully is a threat" and means "the bully poses a risk," then we could enter this in the Risk Log in one of three ways:
  • There is x% chance that the bully will call another worker a bad name, causing that worker to quit.
  • The bully will call another worker a bad name, and there is y% chance that the other worker will quit.
  • There is x% chance that the bully will call another worker a bad name and y% chance that the other worker will quit.
If there is 100% probability that the bully has or will call the coworker a bad name and a 100% probability that the coworker will or has quit, then we have an issue.

And if you go around calling my coworkers bad names, we have an issue.

Further study: Use a search engine to learn more about "aleatory variability" and "epistemic uncertainty." However, please don't ask me about them because, the way other authors explain them, I do not understand at all.

(c) Copyright 2014, Richard Wheeler

04 June 2013

What to Call Risk and Opportunity Management

Many writings lump risk management and opportunity management together under the label, Risk Management.  Risks and opportunities are left-pointing and right-pointing rays on the same line.

Many equate risk with probability, so they drop opportunity from the label. They think of risk as an abbreviation for risk and opportunity. Others worry, then, that opportunity will be forgotten -- as it usually is!

When one speaks of risk [and opportunity], one speaks of the probability that something will happen. That is,

Risk = Probability x Impact, where Impact is a loss

and

Opportunity = Probability x Impact, where Impact is a gain

If risks and opportunities are rays pointing left and right, then opportunities are negative risks. If you deal with them in the same matrix, pay extra attention to your negative signs.

Risk and opportunity management can result in influencing the probability, influencing the impact, or other strategies such as accepting a potential loss or waiting to deal with situations when and if they become an issues.

(Remember that a situation is a risk if the probability lies between zero and one.  A situation is an issue if the probability is one.)

Uncertainty Management

Could we simply call it Uncertainty Management?  Uncertainty would only deal with influencing the probability that something will occur. The face-value of the term fails to imply the other strategies for dealing with risks or opportunities. The name of this knowledge area should reflect the highest-level concepts, not a component concept.

Opportunities and Threats

Another pairing of terms comes from SWOT analysis - Strengths, Weaknesses, Opportunities, and Threats. SWOT analysis is one technique for identifying risks and opportunities.

Opportunities and threats, as a pair, emphasizes the influences or situations that affect or can be affected by a person or project. (In fact, threat implies that the risk event comes from outside, whereas risks can be either internal or external.)  SWOT analysis emphasizes identification of risks. It makes up only a fraction of the whole set of risk and opportunity management processes.

A Common Risk:  Failing to Deal with Opportunities

Many people forget to manage opportunities with the same vigor that they apply to managing risks.  Exploiting opportunities can mitigate the potential impact of risks. The reasoning goes, Risk A may set us back a week, but Opportunity B may save us a week.

PMs have other reasons to exploit opportunities.   Exploited opportunities cut costs, relieve schedule pressure, and improve quality. In short, they maximize profit.

Failure to exploit opportunities wastes resources, causes product lines to stagnate, erodes market share, and results in lost jobs (perhaps your job!) when the company withers.

The failure to exploit opportunities is itself a fundamental risk.

Therefore, referring to the practice as Risk and Opportunity Management calls attention to the oft-forgotten second half of the discipline. 

Remember that semantics is about communicating, not about winning arguments.  If somebody refers to risk management, you know what they mean.  Adjust.

Copyright 2011, 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

05 May 2013

Differences between Risks and Issues in Projects, Part 1

Differences between Risks and Issues in Projects, Part 1

Issues

Updated 1 June 2014

People define issue in many ways, but in project management, issue has a special meaning.

In everyday English, one synonym for issue is topic. An issue is a situation that merits discussion. For example, the issue, what caused the last ice age or is man's contribution to climate change significant compared to factors such as volcanic ash and the variability of our star.

Everyday issues include past, present, and future situations. Discussions about issues may or may not lead to actions. Often, when we say that something is an issue, we imply that people disagree about it.

In project management, an issue is a situation that merits consideration because it affects the project. For example, the vendor left our parts to rust on the dock and will not ship them until they get paid, but our policy prohibits paying for the shipment until we receive and inspect it.

If the issue is significant, the project team will study actions that would reduce or remedy the situation effects on the project. This leads to change requests.

Part 2 (click here) focuses on the definition of risk and explains a side of risk that most PMP prep materials overlook.

Copyright 2013, 2014 Richard M. Wheeler

24 March 2013

Project Management and Open Communications

Project Managers need to guard against setting up an environment where bad news never reaches them. They need to praise and encourage those who communicate risks before they become issues, issues before they become problems, and problems before they become project failures.

Some managers remind me of the Clinton trial in the Senate, following his impeachment in the House.

The Senate set up a rule requiring Ken Starr to keep all the records and evidence in another building. Bringing it to their offices without an invitation would have violated protocol.

Then the majority of senators refused to go view the evidence. A few who did view it said they came away weeping, and the rest (having refused to view the evidence) said that they lacked evidence sufficient to convict.

Does your comfort zone tempt you to maintain willful ignorance? Does your character allow reliance on plausible deniability? The PM has accountability for project success, which any lack of awareness may bring about; but that accountability extends to achieving success ethically.
 
I wonder:  Do PMs ever include ethical lapses as project risks?

08 March 2013

Forcing versus Withdrawal for Conflict Resolution

Is it true that the Forcing conflict resolution technique is worse than Withdrawal?

Withdrawal can have negative or positive consequences. On the negative side, left to themselves, people may escalate the conflict to the point that the PM loses control. While time passes, risks may evolve into issues, or issues into problems.

On the other hand, people may calm down and consider each others' needs and opinions. In time, they may voluntarily find ways to meet all needs, or at least reach a compromise. They might also find a new solution. So the problem may solve itself. It's important for the PM to respect the team's ability to solve problems and allow them "space" to do so.

Forcing always has losers and creates the risk of driving a less-than-optimal solution. People don't disagree about issues unless somebody sees an aspect that the others do not see. Odds are, if you force a solution, you've missed an opportunity to find a better solution.

Forcing also implies showing disrespect for the "losers," so it demotivates them. Their decrease in performace can becomes a drag to the team. The negative feelings and the drag, in turn, affects the whole team's performance.

You may not have time to find better solutions. Although forcing ranks as the worst technique, circumstances may force you to use it. If you force a solution, you need to follow up with the "losers" to identify the negative consequences. This shows respect for their needs and their perceptions. It also allows you to find ways to mitigate any shortcomings in the forced solution.

06 March 2013

The Lobbyist on the Project Management Team

You are the project manager in an aircraft manufacturing company developing a new range of supersonic fighter planes. Since government approval and involvement are essential, you hire a lobbying firm to get government support to prevent unnecessary changes in your project. Which process is this an example of? (Source unknown)
While aircraft manufacturers conduct some research into designs and materials that they can incorporate into new aircraft, governments usually sponsor development of fighter jets.
 
Scope creep happens in almost all defense projects.
 
For example: 
  • The Defense Department wants the aircraft to provide certain capabilities for the Air Force.
  • Then the Navy wants compromises in the design so the jets can take off from carriers.
  • The Army and Marines add their particular use cases.
  • Allies want introperability with their systems.
  • Later, one politician wants to cut costs,
  • another wants the aircraft to use inadequate landing gear designed by the manufacturer in his home town,
  • and over 600 politicians and thousands of bureacrats want to influence the project.
  • Meanwhile, competitors and the nation's adversaries develop new technologies to which the designers must respond.
  • And one of the political parties, along with the press, begin mocking your aircraft by calling it an Imperial Tie Fighter.
If you let it, the politics will multiply the cost twentyfold, drag out the schedule an extra 15 years, and make your company a laughingstock. By the time of the first production run, the aircraft will already be obsolete.
 
The same sort of changes can happen in any project. One way to control the risk of scope change is to refuse to make changes, but too little flexibility can create customer dissatifaction and cost you future business.
 
For a better way to reduce the risk of scope creep, maintain close personal relationships with the stakeholders, keep them informed of the costs of changes, and negotiate agreements that best serve the business case.
 
The PM cannot always do this, so the company hires a lobbyist with exceptional people skills and knowledge of the bureacratic systems. The lobbyist uses various methods to convince the politicians and bureaucrats to resist tinkering with the project requirements.
 
In process terms, hiring a lobbyist does not proceed from the Project Communications Management processes. Lobbying does not contribute directly to producing the product or providing a service. A first pass through the Identify Stakeholders and Plan Communications processes would assume everything goes as planned and would focus on required reporting and coordination. The lobbyist's job goes far beyond that.
 
If the team identifies scope creep as a risk, they make a note to consider it later when they follow the Identify Risks process. They would, at that time, add recruiting a lobbyist to the Risk Management Plan portion of the integrated Project Management Plan.
 
Don't forget that, as a member of the project team, the lobbyist becomes a stakeholder. For example, the team must add the lobbyist's tasks to the WBS and estimated costs during the next iteration of project planning. They must also consider the lobbyist's information needs during the next iteration of the Project Communications Management processes.

24 February 2013

Project Selection

For project selection, the Project Management Institute's (PMI's) Project Management Body of Knowledge (PMBOK) Guide assumes you have more than one project from which to choose. By analyzing the options, you can determine which has the greatest value to the company. The formal method for choosing the best option is called a project selection method.
 
Suppose I have to choose between
  • fixing my child's favorite meal and leftovers for my wife, or
  • fixing my spouse's favorite and cheese mac for my child.
So I ask, "which gives me the better Return on Investment (ROI)?" To answer the question, I consider
  • How much time and money it will take
  • How much of a mess I will have to clean up
  • Does it align with my goals (fun vs. study time)
  • Rewards (somebody else WILLINGLY taking out the trash)
  • How long it will take to reap the rewards
  • Risks (what if I overcook the macaroni? or burn the steak?)
A Project Manager (PM) will place a priority on each criterion and score the probable outcomes. The sum of the weighted scores for each option yields a total score for that option.
I did this with my daughter last year when she needed to buy a car. The result surprised me and was not at all what I expected, but it turned out to be a great choice.

The primary use of project selection is for choosing between projects. However, one can also used it during the project life cycle. The projected ROI of a project can change, for example, due to changing market or regulatory conditions. If the ROI falls, it might be worth canceling the project so the funds and resources can be applied to a more promising project. This is a special case of selecting between competing opportunities.
 
The executives of a company I won't name signed a contract to deliver a product on a certain date. If the company failed to deliver on that date, the company would have to pay liquidated damages; and if the company canceled the project, it would have to pay penalties.
 
Unfortunately, the executives failed to have Engineering review the contract. It turned out that the company could not meet the deadline. The PM tried schedule compression, but as risks turned into issues, it became clear that the project could not meet its deadline.
 
What should they have done? The company should have used the project selection method to choose between
  • Completing the project and paying the liquidated damages
  • Canceling the project and paying the penalties.
Remember, the considerations aren't always directly related to the project. Things such as the company's reputation, the future value of establishing a market presence, or future business based on this project's design work have value, too. For example, cell phone companies often sell cell phones at a loss because they make their money on the service contracts.

Copyright 2011, Richard Wheeler

16 October 2012

Handling a Customer's Wishes

Under what circumstances might change requests to the project's scope be denied? How can i handle a customer's wishes if the scope change is not approved.

Short answer: The Project Manager's (PM's) job is to handle the project's requirements, not to handle the customer's unfunded wishes.

Scope changes always affect schedule, cost, quality, resources, and/or risk. A PM will not approve a change that negatively affects those constraints unless it is necessary in order to meet other, higher-priority constraints. 

Obviously, if adding a bell means going over budget and falling behind schedule, the PM will disapprove it. On the other hand, if the customer will not accept the project because the whistle toots with the wrong tone, then the PM may approve spending more to tune the whistle. 

Remember, these are business decisions. At some point, the penalties for cancelling a project may cost less than the cost of completing it.

The above deals mostly with changes requested internally. If the customer requests a change, the PM will present the customer with the effects (cost, schedule, ...) of the change. The customer then bears responsibility to sponsor or reject the change. 

As always, this is a business decision. Even if the customer will bear the cost, extend the schedule, and forgive any realized risks or impacts on quality, the available whistle-tuners may have been committed to another project (inadequate resources), or the loss of reputation (even though the customer specified the wrong tone) may hurt the business in the long run.

To "handle the customer," get out your requirements traceability matrix and present the effects of the change on the scope. Then present the effects of the change on cost, schedule, etc.

Copyright (C) 2012, Richard Wheeler. Permission granted for use not involving publication.