Difference between Change Control and Configuration Management

Project Management Professional (PMP) students often confuse Integrated Change Control (ICC) and Configuration Management (CM). To put this very simply, ICC controls change whereas CM controls the records of all approved work.

Configuration Management


There are two types of changes. One moves forward whereas the other move backward or sideways. (The are not PMI terms. I use them just to help you picture the differences.)

Forward change is normal work as it happens according to plan. You submit the Project Management Plan and ongoing work to CM when they are done and approved by reviewers. The main purpose of CM is to make sure everybody bases new work on the latest, approved plans and work.

CM also provides and controls the repository for work history, process assets, and lessons learned. Once work has been approved and entered into CM, it becomes subject to change control.

Integrated Change Control 


Backward changes revise work already done. Sideways work requires changing the Project Management Plan or design plans before moving forward. All changes to the plan or to previous work go through ICC. The ICC procedure ensures that you consider the alternative measures and the effects that a change can have. Passing the change through the ICC Board ensures that people with various perspectives can identify stakeholders and impacts you did not think of. This procedure enables making informed decisions.

The change request and the ICC Board's decision are stored by CM. If the change is approved, the change has to be implemented, and the records of the change (for example, approved, revised documents) are stored by CM. CM usually has responsibility for notifying the stakeholders in accordance with the communications plan.

Think of the ICC as the process for making sure changes to existing plans and work are done the right way. Think of CM as the library where all approved plans and work, including changes, are stored.

20 June 2017

When Sales Promises Phantom Features

What should a Product Development or Project Manager do when Sales has sold the product with a feature that does not exist, Engineering does not plan to build it, and it is not in the SOW?

This is like bringing the boss home for dinner without telling your spouse.

In this case, the organization is broken. It is stovepiped, with Sales not considering other stakeholders within the organization.

Some would look at the Statement of Work (SOW) and draw a hard line, but that option often does not legally exist. The spoken word often binds the Seller.

My answer assumes traditional product development and project management. Agile developers have considerable flexibility with scope.

If you don't have a Change Management Process, create one. Your Product Roadmap, Project Management Plan, and product design may require significant rework that must be analyzed and documented. The presumptuous defenestration of all that planning incurs significant costs and delays because they have just altered your carefully optimized route.

Driving is a great metaphor, here. You invested significant creativity and expense in planning to add features and develop your market in a logical order. Now, you have to spend more budget and time on planning a new route that may take longer to get to the destination.

As a starting point for accountability, require Sales to submit a Change Request form that requires documenting the business case, costs, funding sources, risks, schedule impact, and technical impact and feasibility. This requires business analysis and coordinating efforts of many stakeholders such as the buyer, users, Product Development, Engineering, Production, Deployment, Scheduling, Contracts, Finance, Quality, and suppliers (through Purchasing). The change may be a "done deal," but Sales needs to stand before a Change Control Board (CCB) and gain an understanding of the consequences of their actions. When the borrowed experts from Engineering start charging against Sales' budget, even their managers will get the message.

Fulfilling the changes will require a combination of creative options.

  • Most people will compromise rather than spoil their relationship with your company by taking advantage of a loose-lipped salesman; so you may be able to negotiate a change to the contract based on re-prioritizing client needs.
  • Since the change may have value to other customers, management might accelerate investment in product development funding.
  • Consider dipping into Management Reserves and profits.
  • Bring in a Lean/Six Sigma team to find cost and schedule savings. (After that, have them help fix those stovepiped processes.)
  • If the Product Roadmap includes features not delivered to this customer, delay their development.
  • Look for features planned for the product but not promised to the Customer. They may be removed.
  • Sometimes, the penalties for breaking a contract cost less than fulfilling it. This is your worst option, but it is a valid option.

A well thought-out Change Request Form anticipates the areas that require investigation when instigating change. A well-designed Change Control process not only provides opportunity for characterizing changes, but also for creative thinking about the solutions to sticky problems. 

Copyright 2017 Richard Wheeler

19 February 2014

Change Request Analysis or Filing the Change Request -- Which First?

As sample question for PMI's PMP exam asked, in part, whether an analysis should be performed before "raising the change request." I believe that the PMI-approved answer is that, when somebody such as the customer requests a change, the first step is always to analyze the impact.

Defining the Change Request

The answer to this question depends on how one defines submitting, filing, or "raising" a Change Request (CR). If it means submitting the request to the Change Control Board (CCB), expecting its approval, then one definitely should perform the analysis first.

However, I define filing a CR as placing it under control of the CCB. That does not mean that the entire board oversees the CR before it has been analyzed. It means that the CR is entered into a Change Request Log so it can be tracked and analyzed with adequate oversight.

Preventing Duplicated Analyses

Performing the analysis before filing the CR implies that, if the request is not practical, the Change Request may never be filed. That can cause problems.

Suppose the customer suggests a change to the Chief Engineer, and the CE does an analysis of the change. Then the customer suggests the change to the Project Manager, and he does a separate analysis. Later, one of the engineers thinks of the same change and does yet another analysis. Do you see the waste?

To avoid such waste, an organization should have a coordinator act as gatekeeper for the Change Control Board. Each Change Request (CR) should be filed with the facilitator before an analysis is performed. The coordinator can cross-reference the change against previous CRs to identify similar or duplicate analyses that have already been performed. This prevents duplicated effort. The coordinator can also suggest other resources, such as studies or subject matter experts. Or, the coordinator might create efficiency by combining the analysis with another activity.

Tracking Progress

Now, imagine that the customer asks the PM to make a change, and the PM performs an analysis, but it falls off the PM's desk into the trash can and is forgotten. Later, the customer sues the company because it did not make the requested change.

Instead, imagine that the PM filed the CR with the CCB coordinator FIRST, before analyzing the impact. The coordinator would create an entry in the Change Request Log and assign a due date for the analysis. When the due date comes, the coordinator asks the PM, "where's your analysis?"

Objective Evidence

Later, if the customer asks, "Why wasn't that change made?" the PM can ask the coordinator to look it up in the CR log. The PM finds the file number of the analysis and sends a copy of it to the customer.

Controlling the Cowboys

One last scenario: Suppose the hydraulics engineering manager falls in love with a certain change. He takes a week to perform the analysis and then files the CR with the CCB. However, the CCB has a wider perspective and wants the analysis performed by the Mechanical Engineering director in coordination with Purchasing and Manufacturing. The second analysis takes another week. If the hydraulics manager had submitted the CR to the CCB first, they could have saved a week and gotten the change approved earlier, when it was less expensive to make.

Conclusion

The PMI answer may assume that you should not bother the CCB until you have analyzed the change. However, allowing the CCB to coordinate CR analyses can reduce analysis costs, save time, create accountability for completion of CR analyses, increase the quality of the analyses, and ensure that the analyses become part of the project records.