22 November 2018

Difference between Change Control and Configuration Management

Project Management Professional (PMP) students often confuse Integrated Change Control (ICC) and Configuration Management (CM). To put this very simply, ICC controls change whereas CM controls the records of all approved work.

Configuration Management


There are two types of changes. One moves forward whereas the other move backward or sideways. (The are not PMI terms. I use them just to help you picture the differences.)

Forward change is normal work as it happens according to plan. You submit the Project Management Plan and ongoing work to CM when they are done and approved by reviewers. The main purpose of CM is to make sure everybody bases new work on the latest, approved plans and work.

CM also provides and controls the repository for work history, process assets, and lessons learned. Once work has been approved and entered into CM, it becomes subject to change control.

Integrated Change Control 


Backward changes revise work already done. Sideways work requires changing the Project Management Plan or design plans before moving forward. All changes to the plan or to previous work go through ICC. The ICC procedure ensures that you consider the alternative measures and the effects that a change can have. Passing the change through the ICC Board ensures that people with various perspectives can identify stakeholders and impacts you did not think of. This procedure enables making informed decisions.

The change request and the ICC Board's decision are stored by CM. If the change is approved, the change has to be implemented, and the records of the change (for example, approved, revised documents) are stored by CM. CM usually has responsibility for notifying the stakeholders in accordance with the communications plan.

Think of the ICC as the process for making sure changes to existing plans and work are done the right way. Think of CM as the library where all approved plans and work, including changes, are stored.

12 March 2013

Difference between Quality Assurance and Quality Control

Major Differences between QA and QC

The difference between Quality Assurance (QA) and Quality Control (QC) can easily get lost among all the words. Some simple contrasts will help separate the two in your mind.
 
1. QA is primarily proactive. QC is primarily reactive.
 
2. QA focuses on the methods. QC focuses on the results.
 
3. QA uses some statistical methods to analyze how work is done, but QC uses a lot of measurements and statistics to make sure you get the right results.
 
4. QA's scope how the project gets done, whereas QC's scope includes how well the work got done and how well the product or service meet the requirements.
 
Putting those together, Quality Assurance assures you will get the product or service right by making sure the work gets done using the best methods. Quality Control measures and analyzes to control the quality of the product, service, or project execution, and to verify whether it meets the requirements.
 
If you view your studies of QA and QC with this framework in mind, the rest of the differences will make a lot more sense.
 
Example
 
I like food, so let's use a restaurant as an example.  Normally a restaurant would be Operations (not Project), so let's assume that our fine establishment will cater an event and, therefore, Chef Boyardee has a project to manage.

QA (proActive Execution) may find weaknesses in processes or standards due to problems that have occurred. For example, Waiter A wanted to take a break, but Waiter B did not know to whom to deliver the food. We have identified a new stakeholder requirement: Waiters need the ability to hand off orders to each other.

The head waiter improves the process by requiring all waiters to include the table number and seat code for each order. Thus, QA reacts to the problem, focuses on the processes and tools, and enables improvements to the project.

QC (reactive Control) may find a trend indicating an approaching problem. The Chef inspects the food before it is served and notices less steam rising from the tandoori vegetables. Although the food is still acceptable, the temperatures are trending downward.

Before customers start receiving food below the Lower Control Limit of temperature, the Chef determines that the tandoori cook's burners are not getting enough propane. The Chef alerts the cook, who swaps in a fresh propane tank.

Thus, QC Monitored the product, analyzed the data, performed a Root Cause Analysis, and enabled proactive control of an issue before it became a problem.
 
Warnings about Generalizations
 
Remember, "proactive" and "reactive" are generalization to differentiate the two processes. QA (proActive Execution) can be reactive and QC (reactive Control) can be proactive, as well.
Is it safe to say that QA involves polices and procedures ... while QC involves actual work on a product or service?
Yes, as a generalization, it is "safe to say that QA involves polices and procedures ... while QC involves actual work on product or service."
 
One important note: Process and procedure are ambiguous terms, and every organization has its own definitions of them. Both QA and QC can initiate improvements to (processes or procedures).
 
For example, one level of (process or procedure) might instruct personnel to collect the materials and drawings, then have the machinist construct the widget, then have QC inspect it.
 
Another level of (process or procedure) might instruct the machinist how to program the machine, mount the raw materials, push the buttons, release and label the widget, dispose the scrap, and prepare the machine for the next task.
 
From that point of view, QA might perform quality audits to verify that a high level (process or procedure) is being followed, but QC might verify that a detail-level (process or procedure) was followed correctly and with the right results. Both QA and QC involve (processes or procedures).
 
Reminder:  This discussion is just about the major differences. When you look at the details and the ambiguous terms makes it confusing, refer back to the big picture for perspective.

16 January 2013

Project Cancellation

While you are directing and managing your project execution, your sponsor tells you that your project has just been terminated. Will you complete Verify Scope process before closing your project?

Yes, verify scope provides an opportunity for the PM and the sponsor to document the project status at that moment... that can be used for lessons learnt as well for future projects. (Name withheld)

No.

Process 5.4, Verify Scope is the process of formalizing acceptance of the completed project deliverables and includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables.... (PMBOK) Since the project has been canceled, no more deliverables will be accepted. Completing the Verify Scope process would waste resources.
 
Exceptions not indicated by the question
  • The terms of a cancellation could include acceptance of whatever has been completed.
  • The company could preserve the deliverables in their current state for use in future projects, in which case, knowing their quality would have value.
Note 1: If one traces the flow of outputs from the Verify Scope process, the next step for any Accepted Deliverable is process 4.6, Close Project or Phase.
 
Note 2: Documenting the project status at the time of cancellation would start with Work Performance Measurements produced by following process 5.5, Control Scope, the process of monitoring the status of the project and product scope and managing changes to the scope baseline. (PMBOK).
 
The PM would then follow process 10.5, Report Performance, to analyze the project's progress, producing Performance Reports. For the final step, following process 4.4, Monitor and Control Project Work, the PM updates Project Documents, including performance reports and issue logs. (The PM would also make other updates to Project Documents during that preceding processes.)
 
Note 3: Non-accepted deliverables would be subject to the Direct and Manage Project Execution or Perform Quality Control processes (and their design and production partner processes). The Direct and Manage Project Execution and the Close Project of Phase processes might invoke some sort of Disposal process to handle the non-accepted deliverables.

Copyright (C) 2013, Richard Wheeler. Permission granted for use not involving publication.