22 November 2018

Difference between Change Control and Configuration Management

Project Management Professional (PMP) students often confuse Integrated Change Control (ICC) and Configuration Management (CM). To put this very simply, ICC controls change whereas CM controls the records of all approved work.

Configuration Management


There are two types of changes. One moves forward whereas the other move backward or sideways. (The are not PMI terms. I use them just to help you picture the differences.)

Forward change is normal work as it happens according to plan. You submit the Project Management Plan and ongoing work to CM when they are done and approved by reviewers. The main purpose of CM is to make sure everybody bases new work on the latest, approved plans and work.

CM also provides and controls the repository for work history, process assets, and lessons learned. Once work has been approved and entered into CM, it becomes subject to change control.

Integrated Change Control 


Backward changes revise work already done. Sideways work requires changing the Project Management Plan or design plans before moving forward. All changes to the plan or to previous work go through ICC. The ICC procedure ensures that you consider the alternative measures and the effects that a change can have. Passing the change through the ICC Board ensures that people with various perspectives can identify stakeholders and impacts you did not think of. This procedure enables making informed decisions.

The change request and the ICC Board's decision are stored by CM. If the change is approved, the change has to be implemented, and the records of the change (for example, approved, revised documents) are stored by CM. CM usually has responsibility for notifying the stakeholders in accordance with the communications plan.

Think of the ICC as the process for making sure changes to existing plans and work are done the right way. Think of CM as the library where all approved plans and work, including changes, are stored.

20 August 2018

Project Manager and PMP Candidate Resources

I will add resources to this list as I come across them or as you identify them in your comments.  With my budget, the emphasis will be on free resources.

Webinars

Podcasts

  • Elise Stevens @ElisethePm
  • Lean Blog
  • People & Projects
  • Gemba Academy
  • Mastering Business Analysis
  • PM for the Masses
  • http://Manager-Tools.com

Sample Questions and Mock Exams

- Beware outdated content. Don't waste your time with any mock exam whose site does not clearly identify it as based on PMBOK 6.

PM Social Media Communities

- The lists below are in no particular order, and my listing of any group does not necessarily constitute a recommendation.
- Study tip: When studying sample questions posted online, look up the answers in the PMBOK and explain why the best answers are best and the other answers are less than best. Having to form complete thoughts helps you internalize the material and helps others learn, too.

LinkedIn
Google Plus
Facebook
- Requests for stolen IP are rampant in some of the Facebook groups. Please join me in discouraging it.
- Some sellers of test materials post the same sample questions in many PMP study groups, and their questions dominate the less-active groups; so many of the groups add little unique value.

Future Additions to This Page or New Pages

  • Business Analysis Resources
  • Continuous Improvement Resources

31 October 2016

Corrections to LinkedIn's Course, Business Analysis Fundamentals

LinkedIn's inLearning course (apparently they got it from Linda.com), Business Analysis Fundamentals, provides plenty of useable information. However, I was frustrated with a number of points. The most damaging were the course's confusion about Validation, Verification, Traceability, and Stakeholders.

  • You validate requirements by confirming that they have authority, are necessary, and meet standards for quality. Validation looks upward.

  • You verify that requirements are met either by lower-level requirements or by the product. Verification looks downward. Methods include Inspection, Analysis, Test, and Demonstration.

  • The course reversed these distinctions and identified only Test as a method of verification.

  • Traceability links each requirement to directly-related higher- and lower-level requirements. Traceability enables validating requirements' authority and verifying their satisfaction.

  • The course's discussion of traceability focused on metadata about requirements' sources. While such information is useful, it is a very minor part of traceability.

  • Stakeholders include everybody who "has a stake in" the project.  The course focused on external stakeholders. It should have included the project team and other internal relationships such as other projects.

  • The course's definition of Functional Requirements includes activities that the project needs to do to deliver the product. It should also have included what the product does and how well it does it.

  • Since the course only half understands what constitutes functional requirements, it classifies Performance among nonfunctional requirements. Project performance is nonfunctional, but product performance is functional.

  • The course treats Transitional Requirements as a separate category. If the project performs a service, transitional requirements can be Functional requirements; and if the project creates a product, they are usually nonfunctional.

  • The T in SMART stands for Time-bound. The course replaces this with Traceable. The substitution is a good one, but it is nonstandard, and it requires that you include temporal requirements in Specific.

As I said, the course provided plenty of actionable content. I would be proud to work with the instructor, and I would learn a lot more from him that he would learn from me. However, we'd have to work out some issues, first.

31 July 2015

Two Steps toward Making Stakeholder Management Manageable

Two Steps toward Making Stakeholder Management Manageable

The materials I've found about Stakeholder Analysis have not explained much more than the PMBOK Guide explains. What grids other than the Power/Interest grid tell me remains a mystery.

However, I have found two hints that simplify the whole Stakeholder Identification (and Analysis) process.

Divide Stakeholder Analysis 

PMBOK 4 describes Stakeholder Analysis as a single Tool/Technique. I would split off the elicitation of information as a separate technique and call it Stakeholder Survey.

Use a form as you visit around the office eliciting detailed stakeholder information. Transfer that information to the Stakeholder Register at the end of the day. If you put the register on a server and can access it register through Wi-Fi, you can save on data entry time.

Fill in what you can before bothering stakeholders. Then verify that information and elicit the rest, as much as you can, face-to-face. For what remains, you can use a questionnaire.

Simplify through Progressive Elaboration 

Consider an analog in Risk Management: First, you use Qualitative Analysis to identify the key risks. Then you use Quantitative methods to analyze only the key risks.

Now, take these lessons from that model:
  • You don't need to perform full analyses for all stakeholders.
  • You need only a small subset of the information to start.
  • Decide what information you need in order to identify Key Stakeholders.
  • Use the Power/Interest grid to identify Key Stakeholders.
  • Collect further information and perform further analysis only on the Key Stakeholders.

Increase the degree of Stakeholder Analysis through progressive elaboration.

  1. First iteration: Key Stakeholders
  2. High Power/Low Interest stakeholders
  3. High Interest/Low Power stakeholders
  4. Low Interest/Low Power stakeholders

Remember, subsequent iterations should require less information and analysis.

This may be as much a delaying tactic as a simplification, which is what I really wanted. However, reducing, breaking up, and delaying the work relieves some of the stress of a potentially overwhelming process.

22 July 2015

3 Factors in Risk Management: Probability, Impact, and Velocity

Risk Score

Qualitative and Quantitative Analyses in Project Risk Management both take into account Probability (P) and Impact (I). A Risk Score is the product of the two.
Qualitative Analyses use subjective estimates of probability and impact as a screening process that categorizes risks for management, monitoring, or ignoring. Risks placed in the management category go on to Quantitative Analysis and Risk Response Planning.

What about Urgency?

A third value should be considered: Velocity (V), which is the inverse of the time-to-impact.
Seldom can we deal with all risks at once. The value of considering Velocity lies in prioritizing further effort so you have enough time to respond to urgent risks. We would not consider Velocity when assigning risks to the three categories because we want to deal with the important things, not the urgent things. (Consider Pareto's 80/20 rule.)
If Probability times Impact describes an area, then to be consistent, we would add Velocity as a third dimension. That is,
Priority Score = Priority x Impact x Velocity

Another View of the Priority Score

Priority times Impact has another label, which is Expected Monetary Value (EMV). EMV is often used by itself for guiding decisions. If we express the Priority Score as
Priority Score = EMV x Velocity
then we give EMV a weight equal to the weight of Velocity.
The reason we would not consider the Velocity by itself goes back to the principle about the cost of rework. The later you deal with a problem, the more it costs because you have to repeat and fix work that came before. The previous effort becomes wasted, costs rise, schedule lags, and you have to use extra resources to get back on schedule.
Similarly, the longer you wait to deal with a risk, the more rework you have to do. Therefore, we need to factor both Velocity and EMV into prioritizing work: Velocity to deal with urgent risks, and EMV to control costs.

A New Step: Priority Analysis (when needed)

I recommend inserting a new step into Risk Management when there are risks with high velocity and you have to prioritize which risks to deal with first:
  1. Qualitative Analysis with Risk Score = estimated Priority x estimated Impact
  2. Priority Analysis with Priority Score = EMV x Velocity = Priority x Impact x Velocity
  3. Quantitative Analysis with Risk Score plus other factors such as Velocity and Cost Effectiveness
I bring up Cost Effectiveness because you want to ensure that you don't spend $150 to prevent a risk whose EMV is only $100.

Reference

Hall, Harry, PMP, PMI-RMP. 30 Quick Risk Evaluation Tips. PM South. http://www.pmsouth.com/2015/07/18/30-tips/. Accessed 21 July 2015.

28 February 2015

The Black Hole of the Agile World: Systems Thinking

Agile fanatics (excuse me: practitioners) love to do things in tiny increments.

That's OK for products where bite-sized deliveries have value, but it's fantasyland for many real-world projects.

Take, for example, the design of a new car. Sure, you can break the car into systems -- chassis, body, safety package, motor, and so on. Waterfall does that, too, but let's consider the airflow over the body. The airflow is affected by the whole assembly. Every part affects the whole. You can't just design a fender in isolation and say, "Looky, looky, I've delivered value!" No, you've delivered an irrelevant piece of scrap.

In any course on Business Analysis, the importance of a unit on Systems Thinking cannot be overemphasized because the Agile world has completely forgotten its value. 

Before the 1990's, there was a role called Systems Engineer.

That title is still around, but the job is not. At least, the job has become a rare grain of wheat a vast field of tares.

A Systems Engineer had many skills of a project manager, a BA, a Systems Thinker, and a cross-disciplinary engineer, all rolled into one.



Along come companies such as Microsoft and Cisco, dropping the qualifying word from titles such as Network Systems Engineer, Software Systems Engineer, and Server Systems Engineer. Suddenly, every engineer, analyst, and administrator is a Systems Engineer. I wish I had a paycheck for every time a recruiter has contacted me with a so-called Systems Engineer job that turned out to be for an IT admin or a software coder.

True Systems Engineering jobs have become needles in a field of haystacks, and systems thinking has almost been forgotten.

Thousands of Systems Engineers lost their jobs due to decimation of the US Defense sector in 2009. (I proud of myself for not pointing out the predictable political element of that.) They still find three strikes against them:
  1. Transitioning to a different job category such as Project Management or Business Analysis
  2. Getting a foot in the door of a different industry (other than fast food)
  3. Living in a job market where all the growth is in part-time service jobs and has gone to low-skilled workers
Hiring managers would do well to consider bringing in experienced cross-disciplinary, systems thinkers. It would not take much training to bring them up to speed in new roles such as PM or BA.

Have you ever thought of a project as a system of people, or a product as a system of technologies? Systems Engineers do that instinctively, and such integrated systems thinking could prevent a lot of headaches for maturing companies.

Now, if you'll pardon me; I need to clean up a spill in aisle five.

01 June 2014

Differences between Risks and Issues, Part 2

Differences between Risks and Issues, Part 2

Threats; and Another Side of Risk

 
Part 1 (click here) of this series defined issue.

Threat versus Risk

If a situation, such as a cause and its effect, is certain, then it is an issue. With risk, we deal with uncertainty. If the probability of something is zero, it has no uncertainty. If the probability is 100%, again, it has no uncertainty. The term Risk only applies when

0% < probability < 100%

In Risk Management, we avoid the term "threat" because in everyday discussion, "threat" could also mean "promise of harm" or "logical sequence resulting in harm."

For example, a bully "threatens" to call you a bad name. If we believe the bully, this type of threat would be an issue, not a risk, because there is no uncertainty. If we don't care what the bully says, there is no effect, so it is neither a risk nor an issue.

Another side of risk

Most explanations of risk concentrate on the probability of the event. What if the event is certain, but you don't know what the effects will be?

Risk has two real parts:
  • Cause - A condition or possible change in conditions
  • Result - The effect that may happen
Risk has a probabilistic part, too:
  • Uncertainty
PMP study materials usually focus on uncertainty about whether the cause will happen. However, we can also have uncertainty about what effect a condition or change in conditions may cause.

Therefore, a condition (or change) may be certain, but you still have risk if you have uncertainty about the results.

As PMs, we are communicators. We listen. Others often use terms and definitions different from ours. So we ask people what they mean and negotiate a common vocabulary. We do this to control the risk of broken communications.

If we find that somebody says "the bully is a threat" and means "the bully poses a risk," then we could enter this in the Risk Log in one of three ways:
  • There is x% chance that the bully will call another worker a bad name, causing that worker to quit.
  • The bully will call another worker a bad name, and there is y% chance that the other worker will quit.
  • There is x% chance that the bully will call another worker a bad name and y% chance that the other worker will quit.
If there is 100% probability that the bully has or will call the coworker a bad name and a 100% probability that the coworker will or has quit, then we have an issue.

And if you go around calling my coworkers bad names, we have an issue.

Further study: Use a search engine to learn more about "aleatory variability" and "epistemic uncertainty." However, please don't ask me about them because, the way other authors explain them, I do not understand at all.

(c) Copyright 2014, Richard Wheeler

25 May 2014

Influencing without Authority

Does anyone have advice or resources for managing up when you have proposal contributors or stakeholders who are Sr. to you? (Especially when they have no idea of proposal best practices but they still have...opinions). -- Etiak Y.

Learning to influence without authority

I love the way Etiak worded that, "but they still have... opinions."

My inability to manage or influence without authority hindered my own career. I didn't even know until a few years ago that it had a name.

Because my title (Senior Systems Engineer) did not match the titles of the supervisors and directors whom I was supposed to monitor as part of my job, I limited my attempts to influence them, even when they needed somebody to hold them accountable.

Because I did not see myself as having authority and did not know how to "influence without authority," those in authority did not see any reason to promote me. Remaining at the same level for decades will stunt and eventually kill your career.

Challenging authority challenges experience

Be sure you have a good case before challenging the stakeholders. What is the authority of your "best practices?" Have you considered the impact of the changes you want to make? What will stakeholders have to change in their current practices and relationships in order to make the changes you want? Will it really make a difference? Are you sure the customer is ready for the new practices?

Communicating the challenge

You might consider laying out, side-by-side, the old and new ways. Be ready to explain, "if we do it this (old) way, then (problem). The Standard recommends doing it that (new) way, which prevents (problem) and (other benefit)." Appealing to logic does not always work because "old ways" take root in the subconscious. You want them to visualize (fear) the problems of the old way and visualize the benefits (reward) of the new way. Communicating through story can help.

If you get buy-in from the stakeholders who are in your chain of command, then you move from a position of influencing without authority to influencing through the halo effect. That is, you borrow the respect given to those who wrote the standard; and as a representative of those who do have authority, you can get the other stakeholders to at least listen.

Manage issues with change

If you have to ask stakeholders to re-write their sections because you failed to communicate your needs, it will reflect poorly on you. Announce that the format will comply with (standards) at the very beginning. Help them do their parts correctly the first time by describing the purpose and methods at the very beginning. Give them templates or easy-to-follow guidelines.

Be sympathetic when people whine and moan, but remind them of how the new way provides a way to escape the problems of the old way, remind them of the rewards of the new way, and thank them for their flexibility.

More on influence

You can find materials on influencing without authority in various places. I just finished reading The Science of Influence, by Kevin Hogan (Wiley, 2005). Understanding more about influencing others will give you the side benefit of having more power to influence your own behaviors.

(c) 2014, Richard Wheeler

30 March 2014

Training the Software Requirements Engineer

What are different type of training required for a Software Requirement Engineer?

The correct answer is, it depends. Software requirements training should fit with the type of project management used by your organization.

One type of training you don't need

Many people think a software requirements engineer should thoroughly understand programming and software engineering. Obviously, you should know something about the software engineering discipline, but knowing too much can destroy your ability to write good requirements. This happens for two reasons.

First, good requirements should ignore the technology (such as which platform or language is used). This is because requirements should not dictate the solution; they should only define the problem to be solved. Devoting too much study to the technology will bias a requirements analyst toward particular solutions. This makes consideration of alternate solutions more difficult for the design engineers.

Second, requirements elicitation is an art as much as a discipline. Managing stakeholders, conducting meetings, choosing elicitation methods, and choosing methods for representing information require strong skills in psychology and communication. Putting all your energy into learning programming languages and tricks will cost you on the human side. It would be as great a mistake as putting all your energy into market research. You need to know enough about programming to win the respect of the designers and to communicate with them, but your job is to build a bridge between the customer and the designer.

What should I wear? Well... where are you going?

Organizations that work with large systems that integrate multiple technologies tend to follow traditional Project Management and Systems Engineering methods. They use some variation of the Waterfall model, such as the V model.

For a high-level understanding of Systems Engineering requirements methods, I recommend starting with INCOSE's (International Council on Systems Engineering) Systems Engineering Body of Knowledge (SEBOK) and using the SEBOK as a guide to subjects for study. Also consider studying Model-Based Systems Engineering, one subset of traditional methods, and SysML, the modeling language used for MBSE.

Organizations that work primarily with software tend to follow Agile project management methods. In Agile environments, requirements engineers tend to go by the title Business Analyst. I recommend starting with the IIBA's (International Institute for Business Analysis) Business Analysis Body of Knowledge (BABOK) and using the BABOK as a guide to subjects for study.

Agile is a set of principles and not an actual method. I have asked for a recommendation for a book that describes the different methods (such as Scrum and Kanban) but have been told no such book exists; for each Agile method, you need to find a different book.

The requirements methods differ considerably between traditional and Agile. Traditional methods nail down requirements and then negotiate schedule and cost. Agile nails down schedule and cost and then negotiates, prioritizes, re-prioritizes, and drops requirements.

The two methods do share some of the same tools. I suggest studying Unified Modeling Language (UML). UML is not a language, but a set of graphical methods for defining requirements. The most commonly recommended book on software requirements is Software Requirements, 3rd edition, by Karl E Wiegers and Joy Beatty.

23 March 2014

Classes for Technical Writers / Communicators

Any suggestions for what further education pairs well with technical communication?
-- Nicholas
Ask the Right Question

Nicholas has asked the right question -- sort of. I don't think anybody can answer the question for him.
 
A technical communicator translates the Subject Matter Experts' (SME's) geek-speak into plain human-speak. Learning the SME's language will play a pivotal role in success. Even introductory courses in the chosen domain will dramatically shorten the learning curve once he lands a job.
 
The question omits any decision about the domain in which Nicholas will practice. When he chooses a direction, he will be better able to determine the answer for himself.
 
If Nicholas has not chosen a domain, yet, I would suggest that he visit his school's career office and the state employment office and ask, "What industries show growth potential for Technical Writers?" Once he has a list of, say, the top ten fields, he can consider which field(s) would most personally reward him.

After that, he can ask, "What subjects would best help me learn the language of the SME's in that field?"
 
Supporting Skills
An employee does not just sit down and start doing the job. Each job has supporting knowledge areas such as planning work, reporting activities, conducting meetings, and defining and adhering to ethics. A successful employee also looks ahead in the direction that the career and the profession will take. That adds soft skills, management, and industry trends to the list.
 
I will name two of the most important skills Nicholas could add to his quiver.
 
First, the most important SME in anybody's career is the boss. Learning about project management (I suggest PMP Exam Prep by Rita Mulcahey) will help Nicholas:
  • Understand how he can support his manager's success
  • Learn more about organizing his own work
  • Start his climb up the career ladder
The knowledge areas defined by project management standards can also serve as springboards into further studies.
 
Second, the ability to visually model processes and information would help Nicholas in any industry. To that end, he should familiarize himself with the Unified Modeling Language (UML). An Internet search will turn up plenty of tutorials.)
 
UML is not a language (not in my vocabulary, anyway), but rather a set of graphical styles and standards for defining and illustrating relationships between entities and for defining the processes in which entities interact. If Nicholas works in the software field or supports business processes, he will probably need to understand UML, anyway.
 
Basic Life Skills for Success in Any Technical Career
 
People normally associate project management with management and producing products, and they associate UML with software engineering, systems engineering, and business analysis. However, the set of tools these two topics would give Nicholas, and the ways of thinking that they teach, would be invaluable in almost any domain. He can study those areas while thinking about the industry he wants to work in.
 
"Professionals" distinguish themselves by continuously and independently learning. Schools lead students through semi-standardized curricula, but professionals write their own curricula. Nicholas should plan his future studies but bear in mind that:
  • he will continuously update that plan, and
  • he does not have to do all his studying now.

19 February 2014

Change Request Analysis or Filing the Change Request -- Which First?

As sample question for PMI's PMP exam asked, in part, whether an analysis should be performed before "raising the change request." I believe that the PMI-approved answer is that, when somebody such as the customer requests a change, the first step is always to analyze the impact.

Defining the Change Request

The answer to this question depends on how one defines submitting, filing, or "raising" a Change Request (CR). If it means submitting the request to the Change Control Board (CCB), expecting its approval, then one definitely should perform the analysis first.

However, I define filing a CR as placing it under control of the CCB. That does not mean that the entire board oversees the CR before it has been analyzed. It means that the CR is entered into a Change Request Log so it can be tracked and analyzed with adequate oversight.

Preventing Duplicated Analyses

Performing the analysis before filing the CR implies that, if the request is not practical, the Change Request may never be filed. That can cause problems.

Suppose the customer suggests a change to the Chief Engineer, and the CE does an analysis of the change. Then the customer suggests the change to the Project Manager, and he does a separate analysis. Later, one of the engineers thinks of the same change and does yet another analysis. Do you see the waste?

To avoid such waste, an organization should have a coordinator act as gatekeeper for the Change Control Board. Each Change Request (CR) should be filed with the facilitator before an analysis is performed. The coordinator can cross-reference the change against previous CRs to identify similar or duplicate analyses that have already been performed. This prevents duplicated effort. The coordinator can also suggest other resources, such as studies or subject matter experts. Or, the coordinator might create efficiency by combining the analysis with another activity.

Tracking Progress

Now, imagine that the customer asks the PM to make a change, and the PM performs an analysis, but it falls off the PM's desk into the trash can and is forgotten. Later, the customer sues the company because it did not make the requested change.

Instead, imagine that the PM filed the CR with the CCB coordinator FIRST, before analyzing the impact. The coordinator would create an entry in the Change Request Log and assign a due date for the analysis. When the due date comes, the coordinator asks the PM, "where's your analysis?"

Objective Evidence

Later, if the customer asks, "Why wasn't that change made?" the PM can ask the coordinator to look it up in the CR log. The PM finds the file number of the analysis and sends a copy of it to the customer.

Controlling the Cowboys

One last scenario: Suppose the hydraulics engineering manager falls in love with a certain change. He takes a week to perform the analysis and then files the CR with the CCB. However, the CCB has a wider perspective and wants the analysis performed by the Mechanical Engineering director in coordination with Purchasing and Manufacturing. The second analysis takes another week. If the hydraulics manager had submitted the CR to the CCB first, they could have saved a week and gotten the change approved earlier, when it was less expensive to make.

Conclusion

The PMI answer may assume that you should not bother the CCB until you have analyzed the change. However, allowing the CCB to coordinate CR analyses can reduce analysis costs, save time, create accountability for completion of CR analyses, increase the quality of the analyses, and ensure that the analyses become part of the project records.

02 November 2013

Communicating the Organization's Direction: The Missing Ingredient

The average worker could not tell you the vision of the employer.

To some degree, the average worker can perform just fine without knowing the mission and goals of the business. However, knowing the purpose of the work can guide decisions made in the course of the work. Perhaps more importantly, having a known, defined purpose can motivate the worker by providing a roadmap to the work's contribution. It provides a personal connection to the work and to the company. This, in turn, improves performance and retention.

Leadership can improve overall performance by communicating the vision, mission, and goals of the business, as well as the specific objectives of each project. (To cut down on wordiness, I'm going to combine all of those messages and call them the "direction" of the business.)

This topic could take up a whole book, but I will address a portion that I think leaders tend to forget. The specific methods and tools used will vary during the lifecycle of a project. For that reason, I would recommend organizing a more complete description of the topic around process groups or project phases:
  • Project selection
  • Project initiation
  • Project planning
  • Project execution
  • Project monitoring and control
  • Project closure
Defining the direction is part of creating the business plan. Any responsible business owner will create most of those materials and update them regularly. From there, communicating the direction requires breaking each section into a PowerPoint presentation, asking lower-level leadership to give it visibility, putting it to work in the organization, and setting up systems of accountability.

Businesses commonly forget to ensure that the elements of the business direction flow down to projects. Leaders present and promote the direction, but they also need to communicate it through actions that create the processes and provide the tools for carrying out the direction and controlling its implementation.

Just as the business needs to continuously review and refine the direction, the projects need to ensure alignment with the business direction. For example, many project managers set the contract as the highest level of requirements. However, many decisions made within a project depend on the business direction.

Leadership can take one step to communicate business direction by empowering Project Scope Management. They can do this by making available a good Requirements Management System (a tool such as DOORS or CORE). The project managers should then include the business direction's documentation as the top level of each project's requirements. During the project lifecycle, the project can ensure that decisions support the business direction and all requirements trace to the business direction.

Many leaders focus on communicating business direction through presentation. However, they must also communicate it through action. Obviously, actions include specific soft-skill behaviors such as demonstrating the importance of meetings by prompt attendance. But they must invest in resources that empower their teams to use direction as a tool and to use it as the measuring stick of performance.

15 July 2013

CPI: Earned Value (EV) Can Never Exceed Planned Value (PV)


Al succeeded with his very first project!  He was so proud of his project.  The customer was delighted and the Costs Performance Index was 1.1.  Yet, the program manager only graded the project as Satisfactory.  Al is so discouraged.  What was wrong with that program manager?

My new friend Bay -- an old friend of Allen, the new Project Manager -- clearly wanted me to be sympathetic toward his friend.  And he wanted me to share his negative feelings toward the program manager.

That is a shame, I replied.  Bay was studying for PMI's CAPM exam, so I decided to turn the moaning session into a project management lesson.  But you can help Al improve his project management skills if he will learn from this.

What do you mean? asked Bay.

What do you think the CPI of 1.1 means? I asked.

Bay thought a moment and replied, Al delivered more than required?

Why? I aked.

A CPI over 1 is good, and the customer is delighted, so Al delivered even more that what was required.

I baited Bay.  Those are all good things, but too much of a good thing can be bad.

How can that be?  Bay asked.

Delivering too much value might not mean you're efficient.  It might mean you're incompetent or even unethical. I wouldn't worry about that, though.  It's impossible to create a high CPI by delivering extra value.

That doesn't make sense, Bay protested.

Do you know what gold plating means in project management?

Uh-oh.  I see what you mean, he said.  I hoped I had him hooked and ready for the lesson.

The Dangers of a High CPI

Each organization has its own expectation for accuracy in estimating.  10% is a common tolerance, but a former employer of mine expected the final estimate to be accurate within +/- 5%.
  • Since a CPI of 1.1 represents a 10% deviation from the estimate, the PM's estimating skills come into question.
  • A CPI at or above the upper control limit of 1.1 means that planned resources have gone unused.  Managers scramble to find work for their employees.  People could lose their jobs.
  • A CPI above the upper control limit means that the company set aside funds for the project that it could have used to support other investments.
  • As you will see below, plenty of reasons exist for avoiding an excessive CPI.

Extra "Earned Value" Is Hidden

Al's CPI was 1.1.  If AC at completion equaled a Budget At Completion (BAC) of $1 M, then EV must have been $1.1 M because CPI = EV/AC.  That would mean that the PV at completion was $1 M.

While EV>PV is mathematically possible, it is not practically possible.  You will see that a CPI of 1.1 at project completion can only mean that the project underspent by 9.1%.

Suppose the scope says, deliver widgets A1 through A10.  When you create the Scope Management Plan, you schedule reviews to ensure that widgets A1 - A10 get delivered. Delivery of each has a pre-assigned value that is measured in the EV.

Suppose the team delivers widget A11, as well.  The Scope Management Plan assigned Earned Value to A1 - A10.  The customer paid for them.  However, the estimate did not include A11, so the customer did not pay for it and it was not included in the cost baseline. 

Since the Scope Management Plan did not include A11, the Quality Management Plan will not check to see whether it was delivered and the Cost Management Plan has no value estimate to assign to it.  Without assigning value, you cannot measure it or include it in the EV.

EV can precede PV during the project, but it cannot exceed PV at end of project.

For a CPI of 1 at end of project, EV = AC = BAC = PV.  If EV = PV = BAC, the only way to achieve CPI = 1.1 is if AC = (0.9090... x BAC).  This is because
CPI = EV/AC = PV/(0.9091 PV) = 1.1
 Thus, a high CPI at end of project can only result from spending less than planned.

The Dangers of Too Much Value

Gold plating refers to extra value given to a customer.  A company's policy may allow delivering extra value as an investment in future business.  For example, the phone company may sell you a $200 cell phone for 99 cents so you will sign a $100/month contract for the service that goes with it.  They expect to earn back the cost of the cell phone during the life of the contract and the following contracts.

In general, however, gold plating has a negative meaning.
  • Gold plating represents areas in which the project delivers value that the customer did not pay for.  Therefore, it represents a loss to the company.
  • If the estimate did not include the gold plating, then the PM's estimating skills come into question.
  • If the Scope, Cost, and Quality Management Plans do not prevent production and delivery of gold plating, then the PM's project planning and control skills come into question.
  • Even if the project stays within budget, gold plating represents missed opportunities to cut costs and increase the company's return on investment.
  • If the PM delivers significantly extra value, it not only raises an issue of an inaccurate cost estimate, it also raises an issue of whether the Seller overcharged the customer.  This raises an issue of the PM's ethics. 
Assigning planned value to A11 could cause major problems:  Suppose the PM anticipated that the team might deliver A11, assigned value to it, and included it in the EV.
  • The team fails to provide A10 but provides A11. The Cost Management Plan will indicate an EV of 100%, even though the project only delivered 90% of the authorized scope.
  • The team provides A1 - A11.  The customer can say, "your bid included A1 - A10. Since you were able to provide A11, as well, your bid was too high. We are reducing our payment accordingly."  The FFP contract provides the Buyer no protection from this if the Buyer feels he has good evidence that he was overcharged.
  • By stopping the team from delivering A11, the PM could have cut costs and increased profits.  This represents waste and lost profits.
  • Delivering A11 might be nice for the Buyer, but it could also be a white elephant.  Suppose the Buyer is a crop duster and A1-A11 are barrels of insecticide.  If the farmers only need ten barrels of spraying done, the pilot will be stuck with the expense of storing, guarding, and disposing of the extra barrel of poison.  That represents extra liabilities to the crop duster, as well as an extra burden on the environment.  If the Buyer refuses delivery of the extra barrel, you will be stuck with it.  If the barrel gets delivered, the Buyer may sue your company for his losses.

Conclusion

PM's view the CPI the same way you look at any other measurement done as part of statistical process control.  They work to prevent high CPIs by striving to accurately estimate expenses.

PM's also view gold plating as an issue and prevent it through careful project management planning and control.


Copyright 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.
 
IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees when you attend the live session. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

24 June 2013

So You Failed PMI's CAPM Test?

This is your first practical lesson in Project Risk Management. When your customer (PMI) specifies a parameter (x%), determine a safety margin so that, if you take the test on a bad day, you will still pass.

How many times did you read Rita's book? Most people read it AND the PMBOK Guide at least twice.

How many practice test questions did you take? Many people take thousands. (You can easily find thousands of free PMP practice questions on the web, although many are outdated and few will be up-to-date after July 31. CAPM questions are much harder to find.)

When you took the practice tests, did you research the answers you got wrong? Did you research the answers you had to guess at? Memorizing will only get you part way through PMI's tests; you need to dig and understand the material.

If you are taking the CAPM, you must want to become a PMP. Consider studying for the PMP exam. The deeper knowledge will give you understanding that goes beyond mere memorization for the CAPM exam. Also, for the PMP exam, you need to have 35 contact hours. Again, the extra effort would help you with the CAPM exam.

The two books I've heard the best reports about are Rita's books and the Head First books. You can also find many free podcasts on the web and on iTunes.

Two names to look for are Oliver Lehmann and Cornelius Fitchner. Oliver has some free apps and the best sample question on the web. Cornelius has some great 'casts, some of which are free.

Finally, when you have a tough time with some concept or a sample exam question, feel free to ask about it in the Google+ group, "Project Management, PMI, PMP Certification." Ask under the tab "PMP preparation questions." (Out of respect for copyrights, please identify the source of quotes.)

Other than that, I suppose there's not much you can do.

See Also


Copyright 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.
 
IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees when you attend the live session. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

20 June 2013

Make Lessons Learned a Part of Your Culture

An organization with process maturity will close the loop on Lessons Learned.

By closing the loop, I mean that the organization will ensure the capture, distribution, and institutionalization of the lessons taught by the school of hard knocks.

While the Project Manager should identify and collect Lessons Learned, Quality Assurance should categorize and preserve them.  QA should take further steps to communicate the lessons.

First, leaving it to everybody to go searching the LL database does not work.  Like that will ever happen! Ha!

Instead, QA should sort the LLs by function and subject and distribute the information to affected functional managers across the organization.  This ensures that, for example, the Integration Engineers in different programs and at different locations receive the expensively acquired knowledge.  If the functional managers fail to communicate the lessons to their people, upper management should give QA the authority to do so.

Second, QA should incorporate applicable improvements to the Organizational Process Assets.  This way, QA does not merely deposit critical knowledge into the Tribal Knowledge Bank, but actually institutionalizes it.  This introduces accountability when QA audits process compliance.  It also allows the lesson to be moved to a section of the database that lists rationales for historical purposes.  Not every Lesson Learned needs to be researched for normal operations.

Note that this involves Change Control at both the project level and at the organizational level.

As an example, engineers delivered documents to a customer without the necessary review and approval of the Chief Engineer.  The incident led to rework and incorrect customer expectations.

Tribal knowledge had established a channel that would have ensured proper review before release.  However, new employees did not know it, and management had nothing in writing that allowed them to discipline experienced employees who knew better.

Engineering stepped in where corporate management had left a gap.  They instituted processes for document review and approval and for an engineering communications manager to coordinate release of documents to clients.

Thus, an incident led to a Lesson Learned.  The Lesson Learned led to policy and procedural changes.  The new practice became part of the formal procedures and did not get lost in a database that ever researched.


Copyright 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

Agile, Waterfall, and PMI Project Differences

I've been asking about the differences between Agile projects and traditional project management.  Many explanations err by answering the question only from a software or Information Systems perspective.  While Agile primarily appears in the software industry, the different approaches appear in many industries and product areas.

Since the Project Management Institute (PMI) offers both Project Management Professional (PMP)® and PMI Agile Certified Practitioner (PMI-ACP)® certifications, it would seem that Agile contrasts against traditional project management. 

However, it would be more instructive to contrast the Agile approach against the "traditional waterfall approach" of Systems Engineering.  (Refer to the International Counsel on Systems Engineering (INCOSE) for details.)

Agile uses a highly iterative approach that works better when requirements are vague and must be defined over the course of the project.  It is more appropriate for, as an example, the next set of security updates to Windows or the next year's model of the Ford Mustang.

The waterfall approach assumes progressive or phased elaboration of a fixed set of requirements that can be defined, validated, and turned into a design architecture or solution, from top to bottom.

However, Agile methods can still be used for portions of the system, particularly peripheral functions of the software. It is more appropriate for, as an example, the core of MS Project 2015 or a new hybrid squirrel-electric vehicle.

 
Copyright 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

05 June 2013

Study Plan for PMP Certification (Early June 2013)

It's a little late to start studying for the PMBOK Guide, 4th edition, test. First, you have less than two months to join PMI, apply for the exam, prep for it, and arrange a test date, and pass the exam.   Second, the 5th edition is out, so a significant portion of knowledge based on the 4th edition is already obsolete.  Third, lots of people need to retake the exam; so if you need to retake the exam, you will have to re-study for the 5th edition test.
 
Classroom interaction is great, but online training has a lot of advantages, too. With my budget, schedule, and remote location, distance learning is an absolute must.  If I had the budget, I would take the training offered by Cornelius Fitchner at PM-Prepcast. Cornelius is also on Facebook at Project Management Prepcast.
 
I would add some warnings.  Preparing for the PMP exam should not be about learning to take the exam.  Boot camps teach to the exam.   That's alright, as long as you understand that a boot camp is just an orientation.  The learning takes place when you

 - Read the PMBOK Guide at least twice.
 - Master the material in one of the great reference books out there. (1)
 - Research the answers to a thousand or so practice questions. (2)

Finally, join the Project Management, PMI, PMP Certification community on Google+.  When you get stumped by a topic or a sample question, share your question.  We LIKE helping each other because, if something stumps one person, others probably have difficulty with it, too.  Besides, it drives us to learn the material. (3)

Studying for the PMP exam is just a starting point.  Getting a piece of wallpaper may help you get a job, but if you want a career, use your certification as a springboard to deeper studies of PM topics and further certifications.

Footnotes

(1) Rita Mulcahey's PMP Exam Prep has a wealth of information, and the Head First PMP book has gotten a lot of recommendations, too.
 
(2) Cornelius Fitchner has listed a number of free exam question sources on one of his sites. Make sure the questions correspond to the edition of the PMBOK Guide for which you plan to take the test.
 
(3) "Fair Use" allows sharing a limited number of questions for critique or discussion. To be fair to the person who wrote the question, cite the source; and to help the rest of us, provide a link.
 
Copyright 2011, 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

04 June 2013

What to Call Risk and Opportunity Management

Many writings lump risk management and opportunity management together under the label, Risk Management.  Risks and opportunities are left-pointing and right-pointing rays on the same line.

Many equate risk with probability, so they drop opportunity from the label. They think of risk as an abbreviation for risk and opportunity. Others worry, then, that opportunity will be forgotten -- as it usually is!

When one speaks of risk [and opportunity], one speaks of the probability that something will happen. That is,

Risk = Probability x Impact, where Impact is a loss

and

Opportunity = Probability x Impact, where Impact is a gain

If risks and opportunities are rays pointing left and right, then opportunities are negative risks. If you deal with them in the same matrix, pay extra attention to your negative signs.

Risk and opportunity management can result in influencing the probability, influencing the impact, or other strategies such as accepting a potential loss or waiting to deal with situations when and if they become an issues.

(Remember that a situation is a risk if the probability lies between zero and one.  A situation is an issue if the probability is one.)

Uncertainty Management

Could we simply call it Uncertainty Management?  Uncertainty would only deal with influencing the probability that something will occur. The face-value of the term fails to imply the other strategies for dealing with risks or opportunities. The name of this knowledge area should reflect the highest-level concepts, not a component concept.

Opportunities and Threats

Another pairing of terms comes from SWOT analysis - Strengths, Weaknesses, Opportunities, and Threats. SWOT analysis is one technique for identifying risks and opportunities.

Opportunities and threats, as a pair, emphasizes the influences or situations that affect or can be affected by a person or project. (In fact, threat implies that the risk event comes from outside, whereas risks can be either internal or external.)  SWOT analysis emphasizes identification of risks. It makes up only a fraction of the whole set of risk and opportunity management processes.

A Common Risk:  Failing to Deal with Opportunities

Many people forget to manage opportunities with the same vigor that they apply to managing risks.  Exploiting opportunities can mitigate the potential impact of risks. The reasoning goes, Risk A may set us back a week, but Opportunity B may save us a week.

PMs have other reasons to exploit opportunities.   Exploited opportunities cut costs, relieve schedule pressure, and improve quality. In short, they maximize profit.

Failure to exploit opportunities wastes resources, causes product lines to stagnate, erodes market share, and results in lost jobs (perhaps your job!) when the company withers.

The failure to exploit opportunities is itself a fundamental risk.

Therefore, referring to the practice as Risk and Opportunity Management calls attention to the oft-forgotten second half of the discipline. 

Remember that semantics is about communicating, not about winning arguments.  If somebody refers to risk management, you know what they mean.  Adjust.

Copyright 2011, 2013, Richard Wheeler -- Permission granted for non-profit or personal use with a link to this post.

IT Metrics and Productivity Institute (ITMPI) Premium membership gives members free access to 400 PDU-accredited webinar recordings and waives the PDU processing fees. The library is growing at about 100 webinars per year. Check it out: http://mbsy.co/dPHm?s=e

15 May 2013

How to Memorize PMP Formulas

Four Keys to Memorizing Anything

Memorization is like eating my biscuits. You use a knife and a cutting board to cut them into smaller pieces. Then you bite them into even smaller pieces with your incisor before chewing and chewing with your molars, sometimes on the right side of your mouth, then on the left side of your mouth.

Memorizing a formula, you use a pen and paper to break it into parts. Then you repeatedly work on the pieces. Sometimes you write them and sometimes you say them out loud so you involve more than one sense. Unlike my biscuits, you put the pieces back together in medium-sized pieces and chew on them for a while before putting the whole formula together and chewing on it.

The keys so far are
  • Smaller pieces
  • Repetition
  • Multiple senses
  • Reassembly

The Fifth Key to Memorization

The remaining key is (drum roll, please!)
  • Analysis
If you can understand a formula, you can recreate it without memorizing as much of it.

Example:  Point of Total Assumption in a Cost Reimbursable Contract

  • PTA = ((Ceiling Price - Target Price)/Buyer's Share)) + Target Cost
(I have limited the scope of this post to memorizing the formula, so please don't expect an explanation of Cost Reimbursable Contracts.)

The first step in analysis is to restate the formula in a fashion more visually decipherable.
  • PTA = Target Cost  +  (Ceiling Price - Target Price) / (Buyer's Share)
Notice that I turned the formula around.  I like to write formulas the way you would see it graphed: with the biggest portion first, at the bottom. Look at the inconsistent way most people present the Cost Estimating formulas, and taking this liberty will make even more sense.

The contract is Cost Reimbursable, so the first part of the PTA is what we hope the cost will be, the Target Cost.
  • PTA = Target Cost + some ugly fraction
The two price points above the Target Cost are the Ceiling Price and the Target Price. The Ceiling is higher, so it goes first:
  • (Ceiling Price - Target Price)/something
Something is the Buyer's Share.  Sorry, you'll just have to memorize that.

This is the point where you take total assumption of your own learning and put the formula back together. Remember, the keys to memorizing are
  • Smaller pieces
  • Repetition
  • Multiple senses
  • Reassembly
  • Analysis

05 May 2013

Differences between Risks and Issues in Projects, Part 1

Differences between Risks and Issues in Projects, Part 1

Issues

Updated 1 June 2014

People define issue in many ways, but in project management, issue has a special meaning.

In everyday English, one synonym for issue is topic. An issue is a situation that merits discussion. For example, the issue, what caused the last ice age or is man's contribution to climate change significant compared to factors such as volcanic ash and the variability of our star.

Everyday issues include past, present, and future situations. Discussions about issues may or may not lead to actions. Often, when we say that something is an issue, we imply that people disagree about it.

In project management, an issue is a situation that merits consideration because it affects the project. For example, the vendor left our parts to rust on the dock and will not ship them until they get paid, but our policy prohibits paying for the shipment until we receive and inspect it.

If the issue is significant, the project team will study actions that would reduce or remedy the situation effects on the project. This leads to change requests.

Part 2 (click here) focuses on the definition of risk and explains a side of risk that most PMP prep materials overlook.

Copyright 2013, 2014 Richard M. Wheeler